中央空調安裝調試難點分析及處理措施中英文對照
Analysis and treatment measures of difficult installation of central air-conditioning engineering
隨著經濟建設的不斷發展和人們生活水平的不斷提高,中央空調系統已經成為大型建筑和辦公環境不可缺少的重要設施。中央空調的效果如何?能否滿足所需?除設計和施工外,關鍵的一環,在于安裝調試工作的質量,它將直接影響空氣調節的使用效果。本文就中央空調工程安裝調試過程中的難點進行分析,并根據問題原因提出一些處理措施,以便進一步提高中央空調工程安裝調試質量,發揮中央空調應有的效能。
With the development of economy and the improvement of people's living standard, the central air-conditioning system has become an indispensable important facilities of large buildings and office environment.How the central air conditioning effect? To meet the need? In addition to the design and construction, key ring, lies in the installation and debugging work quality, it will directly affect the air-conditioning effect.Difficulties in central air-conditioning engineering installation process are analyzed, and puts forward some measures according to the problems, in order to further improve the quality of installation of central air-conditioning engineering, play a central air conditioning effectiveness.1.空調系統結露
空調系統在運行中發生結露,導致出現風管及吊架結露、風口滴水、天花滴水、墻面滲水發霉、墻面涂料脫落等現象,雖然不會造成太大的事故,但已經影響到了觀感和使用功能,給用戶使用和大樓物業管理帶來許多不便,并造成了一定的經濟損失。其原因為保冷施工不規范,保冷層厚度不達標,保冷措施未發揮作用等等。因此,保溫保冷的施工應聘請技術過硬的施工隊進行施工。air conditioning system of dew condensation in the operation of the air conditioning system, led to the emergence of wind pipe and outlet water, condensation, hanger ceiling dripping, wall seepage moldy, wall paint off phenomenon, although not cause too much of the accident, but has affected the perception and use function, the use and the building property management to bring a lot of inconvenience, and caused a certain economic loss.The reason for the cold non-standard construction, cold layer thickness is not standard, cold measures does not play a role.Therefore, construction of thermal insulation cold for the construction team please skilled construction.1.1風管的處理:目前中央空調風管主要有無機材料復合風管和鍍鋅鐵皮風管兩種。無 1 http://www.tmdps.cn/ 機材料復合風管由兩層高輕度無機材料夾一層保溫材料復合而成,具有質量輕、不燃燒、造價低,成品板材現場切割制作、安裝比較方便等特點,保溫層一般為2cm厚聚苯烯泡沫。由于材料結構比較合理,一般很少出現結露現象,施工前應重點檢查板材有無剝殼、脹板變形等情況。
1.1 wind pipe processing: the central air-conditioning duct mainly inorganic material composite wind pipe and galvanized iron duct two.The inorganic material composite wind pipe consists of two floors with mild inorganic material with a composite layer of insulation material, has the advantages of light weight, not burning, low cost, finished plate making, field cutting installation more convenient, the insulation layer is generally 2cm thick polystyrene foam.Because the material structure more reasonable, rarely dewing phenomenon, should focus on examination of sheet has no peeling, bilge plate deformation before construction.1.2空調水管道的處理:空調水管道溫度低,出現結露的概率比較大,需要重點處理。施工時需嚴格控制供、回水及冷凝水管道和其他管道、風道、梁、柱、墻體之間的距離,常規距離控制在15cm以上,以便于保溫工程的施工及確保保溫質量,對于管道與支、吊架接觸部位,正常情況下需增加木瓦管托,如無條件,也可以局部裹貼橡塑發泡板,再用卡箍收緊。同時需要注意各條管線應單獨進行絕熱施工。
1.2 air conditioning water pipeline: air conditioning water pipe temperature is low, there is condensation probability is big, need to focus on treatment.When construction should strictly control the supply, between water and condensate water pipeline and other pipelines, ducts, beam, column, wall distance, normal distance control in 15cm above, in order to facilitate heat preservation project construction and ensure that the insulation quality, for the pipeline and branch, hanger contact site, under normal circumstances should increase shingles pipe support, such as no conditions, can also partially coated rubber and foam board, and then tighten the clamp.At the same time the need to pay attention to each line should be insulated construction alone.1.3死角部位的處理:風道、水管緊貼梁底、墻邊及穿墻的部位也是保溫施工的關鍵部位,如正常施工有困難,可以先在這些部位做好簡易模具,再采用局部聚氨酯發泡填充,在風道、水管與障礙物接觸周邊表面形成保溫層,以此隔離死角部位與空氣的接觸。1.3 corner parts of the key parts of air duct, water pipe: close to the bottom of beam, wall and wall part is insulation construction, such as the normal construction difficulty, can be the first to die in these parts, and local polyurethane foam filling, in the air duct, water pipe and the barrier is http://www.tmdps.cn/ http://www.tmdps.cn/ formed on the surface of the contact perimeter insulation layer, in order to isolate dead parts and air contact.1.4送風口的處理:一般而言,相對封閉或面積較小的房間及走道的送風口出現結露的可能性較大,梅雨季節尤為明顯,分析原因主要有以下幾點。
Treatment of 1.4 inlets: Generally speaking, the room and corridor relatively closed or smaller outlet dewing possibility is larger, the rainy season is particularly evident, analysis the main causes are as follows.①空調區域內的空氣相對濕度大:夏季,特別在梅雨季節或者雷雨天,空氣相對濕度大,水蒸氣多,空調送風口很容易產生結露現象。
The air conditioning area the air relative humidity: summer, especially in rainy season or thunderstorm days, air relative humidity, water vapor, the air outlet is easy to produce condensation.②空調送風溫差大:在某些時段,冷水溫度比較低,而風機送風量又偏小,引起送風溫差偏大,從而出現結露現象。這時可以適當手動調小風機盤管末端進水閥開度,加大風機送風量,從而減小送風溫差。
The air temperature: at certain hours, cold water temperature is relatively low, and the fan air volume is small, cause the supply air temperature difference is too large, resulting in condensation.At this time can be manually adjustable small fan coil end inlet valve opening, increase the fan air flow, thereby reducing the supply air temperature difference.③送風口為鋁合金材質:目前空調風口大部分采用鋁合金材料制作,由于是金屬表面,結露會比較嚴重。在購置風口時應注意:a)委托生產廠家在鋁合金表面進行噴塑處理,降低風口表面溫度;b)在風口法蘭邊后側敷貼PE保溫條,減少氣流與風口的換熱。由于空調送風量大、溫差小,送風口出現結露現象的概率比較小。
The air outlet for aluminum alloy material: the current air conditioning most of the use of aluminum alloy materials, due to the metal surface, condensation will be more serious.Should pay attention to in the purchase of air: a)commissioned by the manufacturers to spray on the surface of aluminum alloy tuyere, reduce surface temperature;b)PE insulation strip attached to the outlet flange back side dressing, reduce the heat flow and air.Because the air volume large, small temperature difference, the probability of outlet condensation is relatively small.2.空調器噪聲大、有振動 http://www.tmdps.cn/ The 2 air conditioner noise, vibration 集中空調末端設備一般有組合式空調機組、柜式變風量空調器及風機盤管3種。風機盤管體積較小,出現問題的概率小;組合式空調機組、柜式變風量空調器由于體積大,機械設備功率大,出現問題的概率較大,需要逐步排查。
Central air-conditioning end equipment generally have a cabinet type air conditioner sets, VAV air conditioning and fan coil unit 3.Fan coil has the advantages of small volume, small probability of occurrence problem;cabinet combined type air conditioning units, VAV air conditioner due to large volume, mechanical equipment power, the greater the probability problem, need to gradually investigation.2.1檢查設備內部:系統調試前,按規定必須進行單機試運轉,檢查項目包括:空調器內部有無施工殘留物,減振器或墊塊是否安裝到位,底腳螺栓和相關緊固件是否擰緊,風機葉輪是否摩擦蝸殼,軸承是否有潤滑油,電動機皮帶松緊如何等等,以保證設備自身有良好的運行條件。
2.1 internal inspection equipment: before debugging, stand-alone commissioning required by the regulations, inspection items include: the air conditioner has no construction residues, shock absorber or block is installed in place, the foot bolt and the associated fastener is tightened, the fan impeller friction worm shell, bearing for lubrication, the motor belt.How to wait, to ensure that the equipment has good operating conditions.2.2檢查所有與空調器連接的部位是否有軟接頭:空調水管與空調器連接必須采用可曲撓法蘭橡膠軟接頭。風管與空調器連接部位需安裝靜壓箱,靜壓箱的主要作用有兩點:①降低送、回風氣流噪聲;②合理混合并分配氣流。靜壓箱與空調的連接可以用鋁箔復合通風軟管,也可以用三防帆布軟接頭。
2.2 check all parts connected with the air conditioner is a soft joint: air conditioning pipe and air conditioner connecting must adopt flexible flange soft rubber joints.The wind pipe and air conditioner connecting parts need to install static pressure box, there are two main effect of static pressure box: to reduce send, return air noise;the reasonable mixing and gas distribution.Connected static pressure box and air conditioning can use aluminum foil composite ventilation hose, can also use three canvas soft joint.2.3檢查吊桿是否加裝減振墊塊或彈簧減振器:對于風量小的吊頂空調器,由于電動機功率小、振動小,可以在機組基礎與設備吊架橫托之間加裝減振橡膠板墊塊;風量大的空調 http://www.tmdps.cn/ http://www.tmdps.cn/ 器可以在設備吊桿上加裝彈簧減振器,彈簧減振器的選用標準為:設備總質量÷吊桿數量(一般為4根)×(1.3~1.5)(系數),因此在吊裝前需詳細了解設備質量,否則,彈簧減振器選用偏大會影響減振效果。
Check whether the installation of 2.3 hangers damping pad or spring shock absorber for ceiling air conditioner air: small, because the motor power is small, small vibration, damping rubber pad block can be installed between the base unit and device hanger transverse support;air conditioning air volume can be added on the lifting rod spring shock absorber, selection criteria spring shock absorber for: the number of equipment quality / boom(usually 4)×(1.3 ~ 1.5)(coefficient), so we need a detailed understanding of the quality of equipment, before installation otherwise, spring and damper selection bias will affect the damping effect.2.4檢查設備吊架上是否接有其他用途:在空調器吊裝結束后,應在其底部獨立增加角鐵或方管等橫擔形成網架,以作為其他用途吊筋的懸掛支撐,網架的主吊筋固定在空調器周邊,并與空調器保持一定距離,以便空調器檢修。
2.4 check the equipment on the hanger is connected with other uses: in the air conditioner installation ends, should be independent of an increase in its bottom angle or square cross arm form grid, as other uses hanger hanging the support frame, main hanger is fixed on the air conditioner, and keeps a certain distance with the air conditioner, so that air conditioning maintenance.3.局部區域空調效果差
系統調試時出現的局部區域空調效果差的現象,可以從以下幾個方面來排查并處理。
Local air conditioning effect of air-conditioning effect of 3 local area differential system debugging when the poor phenomenon, can from the following several aspects to the investigation and treatment.3.1檢查空調器過濾網是否臟
在施工中,由于施工環境比較臟,灰塵很容易進入設備內部,設備運行一定時間后,過濾網會發生堵塞,造成空調器進風受堵,送風量偏低。3.1 check the air conditioner filter is dirty in the construction, due to relatively dirty construction environment, dust can easily enter the inside of the device, equipment operation after a certain period of time, the filter blockage can occur, caused by blocking the air conditioner air inlet, air flow is low.3.2檢查風閥是否完全開啟 http://www.tmdps.cn/ 3.2 check valve is fully open
風管安裝過程中,由于施工人員不重視或者防火閥聯動調試等原因,送、回風道主風閥未及時開啟或全部打開,造成空調器送風受堵、風量偏低。
The wind pipe installation process, due to construction workers do not pay attention to or fire valve linkage debugging, send, return air main air valve fails to open or fully opened, resulting in air by blocking the air conditioner, low.3.3檢查有無異物堵塞表冷器
3.3 check whether the foreign body blocking the surface cooler
按規范要求,空調冷水管道與設備連接前都需進行沖洗,實際情況中,由于管線比較長、彎頭比較多,或者受現場條件限制以及有些施工人員職業素質不高等原因,造成管道沖洗不干凈,管道內殘渣較多,最終堵塞空調表冷器的進口,影響水和空氣的換熱。
According to the specification, chilled water piping and equipment are required to wash before connection, in the actual situation, because the pipeline is long, bend more, or restricted site condition and some construction personnel occupation quality is not high, resulting in pipeline cleaning not clean, residue in the final jam more pipes, air import table cold, the heat transfer effects of water and air.如果表冷器前管道上裝有過濾器,要及時拆卸清理,如沒有安裝,需拆卸與機組連接的軟接頭,清理表冷器進口。
If the table cooler of the pipeline is provided with a filter, to removing cleaning, if not installed, soft connector dismounting and cleaning unit, a surface cooler inlet.3.4系統內有空氣 3.4 system with air
在冷水管網注水過程中,如果注水速度過快,管網內會殘留大量空氣,水流動循環后,這部分空氣會集中在系統頂部或其他區域,造成局部空調器內冷水不流動或流動不暢,影響換熱。
In the cold water pipe network water injection process, if the injection speed too fast, the pipe network within the residual amounts of air, water circulation, the air will be concentrated in the system or on top of other regions, causing local air conditioning cooling water does not flow or the flow is not smooth, effect of heat transfer.這種情況下,需手動開啟空調器放氣旋塞和打開系統高點排氣閥排氣。由于自動排氣閥 http://www.tmdps.cn/ http://www.tmdps.cn/ 排氣比較慢,因此在施工中,可以在供、回水主管最高點多安裝幾處排氣裝置,在實際工程中,可以在排氣支管上安裝一個三通,三通水平端安裝普通閘閥,向上端安裝自動排氣閥,在管網注水過程中,可以打開閘閥,讓管網內的空氣快速大量排出,正常后再關閉,使用自動排氣裝置排氣。
In this case, the need to manually open air conditioning vent plug and open the system high exhaust valve.The automatic exhaust valve slowly, therefore in the construction, can a few exhaust device installed in return for charge, the highest point, in the actual project, a three is installed on the exhaust pipe, three horizontal end installed ordinary gate valves, the installation of automatic exhaust valve in the pipe network to the upper end, in the process of water injection, can open the valve, let the air inside the pipe fast discharge, normal after closing, automatic exhaust exhaust use.3.5水流量調節分配不合理
3.5 water flow regulating unreasonable distribution 設計人員在設計系統時,根據不同功能區需求及節能要求,在分水器上設置了一定數量的閥門,以分別控制不同場所的水流量,在調試中需調節好這些閥門的開啟圈數,保證每個場所空調水系統的順利循環和流量的合理分配。
Designers in the design of the system, according to the requirement of demand and conservation of different functional areas, the amount of the valve installed in the water separator, water flow of different places, the need to adjust the valve opening laps, ensure the reasonable distribution of each places smooth circulation and flow of air conditioning water system.4.冷水機組制冷量達不到額定值
Cooling capacity 4 chiller amounted to less than the rated value
制冷機組是集中空調系統的心臟,如出現制冷機組制冷量不達標問題,對整個集中空調系統效果有很大影響。造成制冷量不達標問題的原因比較多,難以進行完全的技術分析,筆者在這里只談幾點粗淺的認識。
Refrigeration unit is the heart of central air conditioning system, such as the emergence of refrigeration capacity of refrigeration unit standards are not the problem, has a great influence on the central air conditioning system.The cause of the refrigerating capacity not the problem more, it is difficult to analyze complete technology, know the author only talked a few superficial here.4.1實際冷負荷超出機組制冷量 http://www.tmdps.cn/ 4.1 actual cooling load exceeds the refrigeration capacity 設計時,對于制冷機組的制冷量要求,設計人員已經進行了詳細的冷負荷計算。但在施工過程中,業主有時會在不是設計范圍內的場所增加空調設備,因此,需核對實際空調服務面積是否超出圖紙設計范圍,如超出,冷負荷會比制冷量大,造成機組冷水出水溫度偏高。The design for the cooling capacity of refrigeration units, requirements, design personnel have carried out a detailed calculation of cooling load.But in the course of construction, the owners will sometimes not in design range of places increased air conditioning equipment, therefore, need to check the actual air conditioning service area is beyond the scope of design drawings, such as beyond, cooling load than large refrigerating capacity caused by the unit, outlet temperature of chilled water.4.2冷卻水參數達不到規定要求
The 4.2 cooling water parameters do not meet requirements
冷卻水的水溫和流量是制冷機組運行時很重要的參數,冷卻水溫偏高和流量偏小對制冷機組效率會產生很大的負面影響,對冷卻水參數是否達到規定要求一定要多加重視和檢查。另外,在設計和土建施工時,要盡量將冷卻塔布置在相對空曠的屋面上,塔的數量超過2臺時,需保證相鄰塔的間距為塔直徑的1~1.5倍以上,以保證各塔的進風氣流不受影響。The cooling water temperature and flow rate are important parameters of refrigeration unit in operation, the temperature of cooling water and high flow is small on the efficiency of the refrigerating unit will have a great negative impact, on the cooling water parameters meets the specified requirements must pay more attention and check.In addition, in the design and construction, to minimize the cooling tower is arranged in a relatively open roof, tower more than 2 units, the need to ensure spacing between adjacent tower of the tower diameter of 1 ~ 1.5 times, to ensure that the air flow into the tower is not affected.4.3購置機組要留有余量
4.3 purchase of units to leave a margin 以溴化鋰冷水機組為例,制冷機組在使用過程中,由于機組自身的一些原因,如機組內部鋼板會有輕微腐蝕及溶液參數發生變化,傳熱管堵塞或結垢引起傳熱效率降低等等,都會引起制冷量衰退。在購置機組時,在設計制冷量的基礎上,可以適當增加些投資,購置制冷量、功率大一些的機組,為今后系統良性運行留有空間。
Using lithium bromide chiller unit as an example, the refrigeration unit is in use process, because http://www.tmdps.cn/ http://www.tmdps.cn/ of some reason unit own, such as a slight corrosion and solution parameters change unit internal steel plate, tube blockage and scaling caused by heat transfer efficiency and so on, will cause the refrigeration capacity decline.In the purchase of units, based on the design of the refrigerating capacity, can be appropriate to add some investment, the purchase of refrigerating capacity, power of larger units, for the future of the benign operation of space systems.總之,安裝調試工作直接關系到空調的使用質量。因此,作為工程安裝調試人員,在中央空調工程安裝調試中,應嚴格按照規范安裝,嚴格管理、認真驗收,這樣才能保證中央空調工程的質量,避免各種問題的出現,保證中央空調的使用品質。
In short, installation and commissioning work directly related to the use of air conditioning quality.Therefore, as the engineering installation and commissioning personnel, in the installation of central air-conditioning engineering, should be installed in strict accordance with the norms, strict management, careful inspection, so as to ensure the central air-conditioning engineering quality, avoid all sorts of problems, ensure the quality of central air conditioner.9
第二篇:中央空調安裝調試
1、空調水系統套管分為兩管制、四管制和分區兩管制水系統。兩管制水系統是指有一套供水管路和一套回水管路系統的水系統,夏季供冷水,冬季供熱水。在機房內進行夏季供冷冬季供熱的工況交換,過度季節不可使用。這種系統結構簡單,布置方便,占用的面積小,節省初投資。運行時冷、熱水的水量相差極大。該系統不能同時實現同時供冷和供熱。三管制系統是指冷水管和熱水管分開設置,而回水管公用的系統。冷熱量的交換系統很嚴重,能量損耗大。末端控制和水量控制較為復雜,較高的回水直接進去冷水機組,不利于冷水機組的運行。四管制指 冷熱水系統的供回水管分開設置。投資較大,運行管理較為復雜,管路較多,系統復雜。
2、冷熱水、冷卻水系統的試驗壓力,當工作壓力小于等于1.0Mpa時,為1.5倍工作壓力,但最低部小于0.6Mpa;當工作壓力大于1.0Mpa,為工作壓力加0.5Mpa 對于大型或高層建筑垂直位差較大的冷(熱)媒水、冷卻水管道系統宜采用分區、分層試壓和系統試壓相結合的方法。一般建筑可采用系統試壓方
法。分區、分層試壓:對相對獨立的局部區域的管道進行試壓。在試驗壓力下,穩壓10min,壓力不得下降,再將系統壓力降至工作壓力,在60min內壓力不得下降、外觀檢查無滲漏為合格。系統試壓:在各分區管道與系統主、干管全部連通后,對整個系統的管道進行系統的試壓。試驗壓力以最低電的壓力為準,但最低點的壓力不得超過管道與組成件的承受壓力。壓力試驗升至試驗壓力后,穩壓10min,壓力下降不得大于0.02Mpa,再將系統壓力降至工作壓力,外觀檢查無滲漏為合格。凝結水系統采用充水試驗,應以不滲漏為合格。
3、釘貼法:釘貼法是日前經常采用的一種保溫方法,首先將保溫釘粘在風道外壁上,然后再將保溫板緊壓在風道上,露出釘尖(圖4---56)。保溫釘形式較多,有金屬、尼龍或在現場用鍍鋅鋼板自制的。保溫釘一般要求在矩形風道底面上的問距約2O0mm,側面約300mm ,頂面30O~400為宜。板縫應整齊嚴密,板材或卷材要與管壁壓實、壓平,不得留有縫隙。保溫釘穿透保溫板后,套好墊片,然后將釘尖扳倒壓平即可:粘釘時,宜每排錯開1/2間距,在施下中常會出現在矩形風道的頂面少粘釘或不粘釘的現象,這樣會使頂面的保溫層不能很好地與風道貼實,而造成保溫(保冷)效果降低。保溫板不帶鋁箔時,可外包扎玻璃絲布,再做面層。
4、氣密性試驗的方法之是打壓試驗,即用氮氣充入制冷系統中觀察其壓力變化,以鑒別是否有泄漏。打壓試驗時,要在制冷系統中安裝高壓壓力表和低壓壓力表(使用復合式壓力計也可)。
氮氣可由低壓側充入。試驗時,高壓壓力不超過1.6MPa(16kgf/cm2),低壓壓力不超過1.0MPa(10kgf/cm2)。充入氮氣后可觀察壓力表,經8小時未見明顯的壓力變化即為合格:若壓力有所變化,應該用肥皂水進行檢漏,以查明漏點。
第三篇:商用中央空調-安裝商用中央空調分析
商用中央空調--商場安裝中央空調分析
商場常用的空調:
1)空調系統的分區
百貨商店各層樓面幾乎都是沒有間隔的通間,沒有必要按朝向的差別進行分區,而應按房間用途進行分區。例如:按一般商場、特種商場、地下商場、商品展示廳、辦公室等進行空調系統的分區。有的大型百貨商店還附設有美容室、餐館、影劇院等設施,由于這些房間的服務時間不同,以及為避免氣味的相互串通,應單獨設立空調系統。2)集中式低速單風管系統
該方式的優點如下:保證有足夠的新鮮空氣;可集中進行空氣過濾和空調機組的消聲處理;在過渡季可采用全新風供冷,可推遲或少開制冷機;由于空氣集中處理,系統本身簡單,維護管理方便。缺點是風管斷面較大,占用建筑空間多。當營業廳內無特殊臭氣發生,且大廳布局變更不大時,集中式低速單風管系統方式是最經濟的。3)新風空調機組加各層機組方式
新風由新風空氣處理機組集中處理,由送風立管(或新風豎井)送至各層,與室內回風混合后,經各層空調機組進行熱濕處理后由風管送入室內。這種系統機動靈活,用得較為普遍。4)集中式低速單風管和各層機組結合方式
在多層商場中,用得較多的是集中單風管和各層機組結合的空調系統。商場的回風經回風立管集中至屋頂或室內空調機組,經集中空氣凈化后,與新風混合、熱濕處理后送入主風管。其優點是在過渡季可全部采用新風供冷及全部排風等。
5)為了節省機房面積,在層高允許的條件下,可采用臥式吊頂機組的空調方式,如大型商場沿長度方向設置多臺吊頂式中、小型臥式變風量空調機組。此時新風進口面積按商場過渡季節送全新風考慮。但必須處理好冷凝水排放問題。
6)中、小型商場或與商店營業時間不同的其他一些房間(例如值班室、電視監視室、配電室和食堂等),采用單元式的空調機組(制冷劑直接膨脹式)比較合適。
7)在寒冷地區底層主要出入口,建議安裝熱空氣幕,以減少或防止非調節空氣滲入,這在供暖時特別需要。
8)百貨商場的辦公室大多設在建筑物的外區,可以采用側送風、風機盤管或者熱泵機組等周邊系統方式。
9)商場內,由于人體負荷大,從人體散發的濕量多,因此外墻的玻璃窗面容易結露,在局部地區,可能會出現濕度過高現象,從而導致商品質量下降,所以在空調系統中,不設加濕裝置。但在出售家具、木工制品的商場內除外。
10)空調冷熱源較多使用往復式和離心式冷水機組,如受到供電容量的限制,也有使用溴化鋰吸收式冷水機組的。在機房面積緊張或不允許采用鍋爐供暖的地方,空氣熱源熱泵是常選擇的一種方式,機組可直接置于屋頂等室外。
商場空調負荷特點如下 :
1)商場內人員密度(包括顧客和營業員)在一天內變化懸殊,它決定于商場客流量,而商場客流量隨時間、平日、節假日、季節、所在地區(鬧市區或郊區),以及商場特色和層次等因素有關。2)商場建筑的空調冷負荷中,除建筑傳熱和日射等外部負荷以外,還有人體、照明、自動扶梯和陳列櫥窗等負荷。3)商場建筑總冷負荷中,人體負荷和新風負荷是主要的。所以合理確定人體負荷是很重要的。
4)商場的建筑傳熱負荷遠小于人體、新風、照明負荷,一般占總負荷的1%~7%。
5)新風負荷在商場建筑中,空調系統的最小新風量是根據人的衛生標準確定的。它與人們在空調環境中所處的狀態、停留時間的長短,以及是否允許吸煙等條件有關。
建筑特點結構:
商場建筑的功能不同于旅館和辦公樓建筑,室內空調一般有以下一些特點 :
1)商場建筑空間大,室內人員多,照明設備多,故空調冷負荷和新風負荷大。
2)商品種類多,營業廳布局常有變動,要求空調設備具有一定的靈活性。
3)大商場內有些營業廳人員密度大,有些密度小,在確定空調機組容量和空調分區時,應加以區別。
4)有些商業建筑趨向多功能化,除了商業空間外,還設有會場、劇場、餐廳等,其空調系統應考慮分區。
5)百貨大樓的出入口人流頻繁,在寒冷地區的冬季,為防止或減少室外冷風的侵入,往往要設置前室并使用熱風幕,在建筑上應考慮合適的入口方位,并設避風用的擋風壁。
6)在過渡季,為了推遲或少開制冷機,應充分利用新風供冷。7)根據建筑防火規范的要求,設置防排煙裝置。
商用中央空調工作原理:
大型商場中央空調原理—大型商場中央空調工作原理
大型商場中央空調原理是由一臺主機通過風管或冷熱水管來連接多個末端的出風口,能夠把冷暖氣送到不同的區域之內,從而實現調節室內溫度的主要目的。中央空調系統一般由冷熱源系統和空氣調節系統共同組成,制冷系統能夠提供所需的冷量,而制熱系統提供所需的熱量,其中制冷系統是中央空調系統最重要的部分,需要認真進行研發和設計。
大型商場中央空調原理—大型商場中央空調的優點介紹
大型商場中央空調具備著多方面的優勢體現,首先它具有投資成本低的特點,可以給人們帶來很高的經濟效益體現。其次大型商場中央空調具備美化裝飾的作用,進行隱藏式安裝,能夠節省室內的占地空間。第三大型商場中央空調具有舒適度高的表現,能夠在運行的時候即使補進新風,不僅能夠提高空氣的質量,也會給人帶來舒適化的感受。第四大型商場中央空調具有結構緊湊、運行穩定的特點表現,在使用效果方面是非常穩定的,不會出現忽冷忽熱的情況。以上介紹的就是有關于大型商場中央空調原理以及大型商場中央空調優勢方面的具體內容,大型商場中央空調是一類具有多方面優勢特點的空調類型,這也是它備受關注的原因所在。裝了中央空調的商場客流量也會更多一些,夏日炎炎,誰都想找個涼快的地方逛逛也好,走走也好。中央空調的制冷效量是可以滿足客流量大的地方。而且現在的時代商場安裝中央空調已經是很平常的一件事,中央空調算是一個大型商場的標配了吧。所以,商場安裝中央空調這件事是利大于弊哦。
第四篇:綜采設備地面調試安裝措施
一、工作面電纜鋪設:
1、電纜在入井前應進行絕緣搖測,對電纜的傷口或外套磨損嚴重的地方,要進行熱補或冷補的修復工作,對于電纜連接的設備是用插頭連接的要將電纜插頭安裝好,電纜絕緣處理好,插頭也安裝好后要將所有的電纜頭用絕緣膠帶纏好或插頭要用塑料布包好,并在電纜頭1米附近標出是電纜所帶的設備,以及是電動機側還是開關負荷側,是移動變電站低壓側還是開關電源側,如果是移動變電站之間的連線,還應標出是幾號移動變電站的連線。
2、這個工作面在電纜的鋪設中采用了先將電纜入井掛在切眼的煤壁上的辦法。電纜鉤要提前掛好,間距不要太遠2.5米以內,塑料電纜鉤太脆容易斷裂,鋪設電纜時不得用力過大,最好要在塑料電纜鉤之間加設鐵電纜鉤,沒有鐵電纜鉤可以在塑料電纜鉤之間用鐵絲捆綁,分擔電纜鉤的承載力。主運轉載機的安裝地點采側的煤壁上沒有電纜鉤,可以將電纜用鐵絲吊掛在頂板上,一定要固定好,否則會出現電纜插頭掉落的事故。各電纜在主運順槽中預留的余量,轉載機電纜45米、破碎機電纜40米、采煤機電纜45米和運輸機機頭電纜高低速各20米。切眼中,采煤機機窩處要將電纜掛在頂板上,以防影響采煤機的安裝。
3、電纜掛入切眼的應注意的幾個問題:1)電纜的絕緣應定期進行搖測,去除浸入電纜內部的潮氣,搖測后要將塑料布重新包扎好;2)電纜要定期巡查,對斷裂的電纜鉤要及時補換。3)在工作面設備的安裝過程中,容易將吊掛在煤壁上的電纜擠壞,要安排人看好,4)電纜在搬家隊易碰撞處貼反光標識進行提醒保護。
4、工作面電纜的入槽和上架:工作面轉載機、運輸機、和支架,以及設備列車到位后。設備列車后面電纜,如果用單軌吊或用皮子抱捆,單軌吊應安裝到位或最好皮子應準備好,還有運輸機機尾上的電纜槽子,機尾入井前應提前安裝好。由于電纜先期已吊掛在煤壁上了,不需要大量的人力來拖電纜,只需要少量的人員,按電纜在煤壁上的次序,由下而上,逐漸放運輸機的電纜槽內。電纜頭在所連接的電動機處應留有1.5--2米的余量;電纜在運輸機機頭入槽和機尾出槽處都應留下1米的余量。電纜要入槽過程中應安排專人對電纜的破口和冷補或熱補的位臵,對應支架的編號一一記錄下來;采煤機的電纜應從主運拉著頭到運輸機機尾留出5米的余量后,從分中槽往運輸機機頭方向數3個電纜槽處由下槽轉到上槽。工作面的660供電電纜也要同時輔入電纜槽入。
二、設備列車安裝須注意的幾個問題:
1、參照過去設備列車的布臵和結合本工作面對設備列車對設備布臵的需要,確定設備列車的布臵順序,并畫出布臵圖。
2、對設備列車所需要的材料要提前準備好。
1)設備列車的照明包括照明燈、電纜、燈架和固定燈架用的螺栓; 2)設備列車的接地裝臵包括接地扁鐵、接地連線、接地極、接地鍍鋅螺栓和移動變電站及綜保輔助接地用的接地線;設備列車的連接板和連接銷。
3)設備列車上的電纜架和電纜插銷,在入井前都應安裝到位,包括空壓機后的特殊電纜架子都應安裝到位; 4)設備列車用的軌道、道夾板和螺栓;
5)設備列車中,移動變電站后面掛電纜用的特殊電纜鉤;
3、設備列車的所有設備在入井前要檢查,除塵除銹重新噴漆,對缺損的零部件要及時補齊和修復。
4、根據過去工作面和所用電纜的長度,確定設備列車尾車到運輸機機尾的距離。
5、設備列車在安裝時,與采側煤壁的距離要適當比生產時寬一些,靠采側道軌采側邊緣與煤壁應留出1.4米至1.5米的余量,方便電纜上架和列車后水管的折除以及液壓管理的吊掛。
6、設備列車入井時應編號和標出朝向工作面的方向。
7、對設備列車上容易丟失部件要另行集中運輸或對其進行固定。
8、對設備上個車上容易損壞的部位要如開關的觀察窗要采取措施進行防護和隔離開關手把。
三、輔運順槽電纜的鋪設和高壓接線盒的安裝
1、輔運順槽的電纜鉤要提前安裝或補齊
2、提前準備好材料包括高壓電纜、高壓接線盒、接地極、接地線、固定接線盒的膨脹螺栓、絕緣膠帶、四氯化氮、凡司林和高壓接線盒內接線用的特殊套筒。
3、電纜入井前要搖測其絕緣程度,對損傷的外套要修復好,并用塑料布將電纜頭包好。接線盒入井前要對保證其完好,缺少零件的及時補齊,生銹的外殼要除銹,重新刷漆。
4、電纜要拉直接線盒處留有的余量不要多過,不要與其他電纜交叉。
5、在施工的過程中接線盒接好線后及時吊掛起來。
四、工作面安裝期間的臨時供電方案
方案1:在最近的配電點660V移動變電站處或截面足夠大的660電纜接線盒處引線,用鋪設好的高壓電纜將低壓電供入工作面。
方案1:在最近的配電點10KV高防開關處或截面足夠大的高壓接線盒處引線,用鋪設好的高壓電纜將高壓電供入在工作面設備列車前的躲避硐中放臵的一個660V移動變電站中,然后用低壓電纜向安裝期間的工作在臨時泵供電。
五、工作面內部設備的安裝
1、中雙刮板鋪設安裝時就注意的哪些事項:
1)刮板的方向應使大弧形面朝向運行方向,使T型螺栓頭指向背離溜槽中板,卻刮板在上槽時,T型螺栓應從下向上穿。2)T型螺栓的六角防松螺母必須擰緊,對直徑42×145 mm的中雙鏈,鏈間距為220mm,每8個環安裝一個刮板,刮板間距為1168mm。3)將聯結件的粘附物清洗干凈,涂少量潤滑油。
4)圓環鏈立環的焊口背離溜槽中板,即上鏈立環焊口朝上,下鏈立環焊口朝下。
5)接鏈環應在豎直位臵,便于通過鏈輪,固定零件不得缺少。6)螺紋的緊固力矩為1320N.m
2、工作面設備供電和通迅、照明系統的安裝: 0)各設備的電動機在入井前應進行絕緣搖測,絕緣達不到要求的要進行處理;電動機不完好的要把各零部件補齊。
1)工作面各設備電動機、開關和移動變電站的接線,嚴格按照接線工藝進行施工,不得出現不完好和失爆現象;使用連接器連接的設備,電纜的連接插頭在受力后容易使內部連接脫開,應打開檢查后再安裝。
2)對于雙速電動機,各電纜和繞組的連接要一一對應,不對接錯:
3)按照供電的電壓等級對設備電動機的接線方式進行施工; 4)移動變電站在通電之前必須將主、副接地裝臵安裝到位; 5)在供電初期,必須先保證一臺乳化泵和采煤機的供電; 6)開關通電后,控制臺以及控制線路也及時安裝,、對開關的所有回路進行先期試車;
7)工作面的通迅和照明燈的安裝,應尾隨支架的安裝逐步展開。所需的材料要提前準備包括,工作面用的擴音電話、通訊電線,固定擴音電話用的架子和螺栓、吊掛電纜用的電纜鉤、支架燈、接支架燈用的電纜、固定支架燈的螺栓。
8)支架的管路要尾隨支架的安裝及時連接,編號要及時標噴出來。
9)工作面的擴音電話要與設備列車控制器及時連通,保證工作面的通訊。
3、工作面采煤機安裝時應注意哪些事項: 0)采煤機在入前必須對各電動機的絕緣程度和各部件的完好程度進行嚴格檢查,缺少的要及時補齊。
1)工作面安裝地點應有足夠的長寬的缺口,俗稱機窩,便于存放采煤機部件。
2)安裝地點的項板支護要完好牢靠,底板清掃干凈,通風良好。3)準備好材料:起吊環、鋼繩繩套、手拉葫蘆、方形枕木、液槍和液管。
4)起吊部件或單體擠壓部件時附近不得站人員,指揮人員應就地選擇安全地點。
5)電工作業與機工用電時,應避免平行作業,防止誤傷害。6)電工應嚴格按照接線工藝和防爆標準進行施工,線路不得出現遺接漏接錯接現象。
7)電工嚴禁帶電作業,機工嚴禁設備運轉時檢修,一定要及時停電閉鎖。
8)各電纜容易受損傷的地方,再試機前要用皮子包好。9)采煤機照明裝臵也要在試機之前要施工完成。
4、刮板輸送機空載試運轉時應怎樣檢查: 1)檢查電纜吊掛、開關,控制器是否工作正常; 2)檢查各減速箱和潤滑點的油箱是否缺油; 3)檢查輸送機上有無人員作業,有無障礙物;
4)按順序點動機頭低速電動機、機尾低速電動機、機頭高速電動機和機尾高速電動機,檢查其旋向是否一致,不一致的要及時整改。5)檢查機頭、機尾摩擦離合器、減速器、各連接螺栓鏈輪、分鏈器、護板和壓鏈塊是否完好、緊固,潤滑是否良好。
6)檢查中間部:從機頭鏈輪開始,往后逐級檢查刮板鏈條、刮板、連接環及螺帽是否正確堅固。檢查4-5米后,在刮板上做個明顯記號;然后開動電動機,把帶記號的刮板運行到機頭鏈輪處;再從此記號向機尾檢查,一直到機尾;在機尾處的刮板再做個記號,然后從機尾往機頭檢查中部槽、鏟煤板、擋煤板的情況。回到機頭處,開動電動機把機尾有記號的刮板運行到機頭鏈輪處,再往機尾重復對刮板鏈檢查,直到機尾。到此,對刮板鏈檢查了一個循環。在檢查中發現的問題要及時處理。
7)緊鏈:輸送機空載運轉后,各溜槽消除了間隙,刮板鏈必然要產生松弛現象,因些,必須重新進行緊鏈。
5、采煤機在工作面安裝試運轉應注意的問題: 外觀檢查
1)零部件完整齊全。螺栓、螺釘堅固,手把及按鈕動作靈活、正確。2)油質和油量是否符合要求,有無漏油、漏水的現象; 3)用手盤動滾筒,不應有卡阻現象。截齒和噴頭齊全完好。4)電動機的接線是否正確,滾筒旋轉方向是否正確,兩牽引電動機是否旋向一致。
5)電纜夾是否齊全,長度否合適,拖纜裝臵是否固定好。6)電控的外圍設備包括端頭操作站,預警裝臵是否安裝到位。7)搖臂上截割部的漏油口是否暢通。8)運輸機閉鎖裝臵是否安裝到位。試運轉應注意:
1)機器應無異常響聲,各部 溫度應正常,符合規定。
2)滾筒升降靈活,升降到最高點和最低點的時間是否符合規定。3)內外噴霧良好,無漏油、漏水現象 4)牽引正常,控制靈活。
5)遙控操作和各操作點的操作是否靈活。
六、伸縮帶式輸送機的安裝:
1、伸縮帶式輸送機在井下安裝前應做哪些準備工作? 0)伸縮帶式輸送機所用的電動機入井前要進行絕緣搖測,開關要開蓋檢查,確定設備完好。
1)設備下井前,安裝人員必須熟悉設備和有關圖紙資料。根據礦井巷道的運輸條件,確定設備部件的最大尺寸和質量。
2)在安裝輸送機的巷道中,首先確定輸送機的安裝中心線和機關的安裝位臵,將這些基準點在支架或頂板相應位臵上標志出來。3)清理巷道底板,根據輸送機總體裝配圖所標注的固定安裝部分長度,將巷道底板平整出來。對安裝非固定部分(主要指落地式機身)的巷道也要求一般的平整。
4)為便于運輸,應將大件解體,并作好標記,以便于對號安裝,對外露的加工面,應采取保護措施,防止磕碰損傷。
2、伸縮帶式輸送機在井下怎樣進行鋪設安裝? 井下鋪設的方法是: 1)井下巷道空間較窄,為避免鋪設時零部件的堵塞,應按照先里后外的原則,即按機移動機尾裝臵、機身(中間架)、回空輸送帶下托輥、縱梁上托輥、載貨輸送帶、卷帶裝臵、儲帶倉(包括張緊小車,移動小車,托輥小車、儲帶倉架、儲帶轉向架車)機關傳動裝臵的順序,搬運到各自的安裝地點的巷道旁邊。
2)根據已確定的基準點,首先安裝固定部件,如機頭部、儲帶倉、機尾等部件。安裝后,機頭尾及各滾筒中心線應在同一直線上。3)安裝機身時首先將H形中間架每3米一架臥放在輸送機中心線底板上,底腳朝向機頭。
4)將輸送帶工作的一面向上,沿輸送機鋪設在巷道一側底板上,然后從一端將輸送帶180度搭在中間架的橫梁上;再裝中間架的縱梁、下托輥與上托輥。
5)輸送機的沿線通訊保護系統,同時推進安裝;
6)鋪設載貨輸送帶可借助主傳動滾筒和另設臵一臺牽引絞車進行。7)用于后退式采煤方法時,將儲帶倉中的游動小車臵于靠近機頭端(前進式或綜掘工作面臵于遠離機頭的一端),開動絞車,給輸送帶以足夠的張力,以保證輸送機在起動和運行過程中輸送帶不會在傳動滾筒上打滑。
8)檢查各部分安裝情況,清除影響運轉的障礙物,做好通訊聯絡,檢查電控保護裝臵動作情況。
9)如果輸送機中間設有中間驅動,中間驅動和帶式輸送機機頭供電應取自同一個電源,所有電動機應設立反饋點,保證電動機在同時工作。
3、制作輸送帶接頭時應做哪些準備工作: 1)按輸送帶的厚度選用相適應的釘扣機和U形扣; 2)切割接頭時,要保持接頭與輸送帶邊呈90度; 3)接頭兩側應切去一個三角形,其高度為25~30; 4)U形釘的尖端應向著輸送帶承載的一面; 5)鋼絲繩聯接銷的長度應小于輸送帶寬度。
4、帶式輸送機的試運轉:
1)未裝輸送帶的試運轉:機頭、儲帶倉和電氣設備都裝好后,先不裝輸送帶,進行空運轉,檢查減速器運轉是否平穩,軸承聲響、溫度是否正常,張緊絞車是否性能良好
2)裝上輸送帶后的空運轉:拉緊輸送帶:在空運轉前,開動張緊絞車給輸送帶以足夠的張力;空運轉試驗:空運轉時全線各點都必須設人觀察情況,發現輸送帶跑偏、打滑及其它不正常情況,應立即停車進行處理,空運轉時間為4小時左右。
3)負荷運轉:空運轉確認無問題后方可放煤加載運轉試驗。驅動裝臵應運行穩,不允許出現異常振動及聲響,在起動和運行過程中不允許輸送帶有打滑現象;運行過程中,輸送帶邊緣不得超出托輥管體和滾筒邊緣;負荷運轉試驗時間為2小時。
5、怎么處理輸送機跑偏?
1)輸送帶在卸載或機尾滾筒跑偏的處理:利用滾筒軸承座上的調整螺桿進行調整,即輸送帶往哪邊跑就調緊哪邊的螺桿。滾筒調整后必須按規定重新調整刮板清掃器。
2)輸送帶在中間部跑偏的處理:利用改變托輥的方向與位臵進行調整,即輸送帶往哪邊跑就在這邊將托輥朝輸送帶運行方向偏轉一個角度,但一次不能調整得太多。
捆綁大件時,應在棱角處墊上舊皮帶,以免損壞鋼絲繩。地面起吊重物時,鉤頭下嚴禁站人,所有人員站在安全地點并戴好安全帽。
安裝過程中起吊設備時必須遵守下列規定: A.起吊工器具必須完好齊全。
B.起吊前要進行試吊確保無問題后方可起吊。C.起吊設備下嚴禁有人工作行走或逗留。D.起吊工具器必須有專人檢查。
使用倒鏈起吊大件時,人員必須站在被起吊物件的側上方和索具受力方向的相反位臵,防止倒鏈或索具滑扣、斷裂傷人。起吊工器具必須完好齊全。
B.起吊前要進行試吊確保無問題后方可起吊。C.起吊設備下嚴禁有人工作行走或逗留。D.起吊工具器必須有專人檢查。
7、起吊設備前,人員必須站在被起吊物件的側上方或索具受力方向的相反位臵,防止倒鏈或索具滑扣、斷裂傷人。
第五篇:管道安裝中常見問題的分析及處理措施
管道安裝中常見問題的分析及處理措施
1、排水管道堵塞問題的預防和處理措施
產生的原因:室 內排水管道堵塞是建筑安裝工程施工中常見的一種質量通病,是管道安裝與土建施工配合難以解決的老問題。在土建與安裝交叉施工中,管道被堵塞的事例很多,特 別是衛生間排水管口與地漏更為嚴重。即使管道安裝后,管口用水泥砂漿封閉,還往往被人打開,作為清洗水泥及平整地面的污水排出口。有的甚至從屋面透氣管 口、雨水斗落入木條、碎石、垃圾、砂漿等,造成管道的堵塞。輕者耗工疏通,重者鑿打砼地面,返工拆除管道重新安裝,這樣既耗工耗料,又影響工期。有的排水 管道管腔內已部分堵塞,在通水試水過程中未能及時發現,投入使用后,必然出現管道堵塞,影響用戶使用。
預防和處理措施:為 了避免交叉施工中造成管道堵塞現象,在管道安裝前,除應認真疏通管腔,清除雜物,合理按規范規定正確使用排水配件;安裝管道時,應保證坡度,符合設計要求 與規范規定及排水管口采用水泥砂漿封口等措施外,還必須采取如下多種技術措施以防止管道堵塞:由于建筑結構需要原因,當立管上設有乙字管時,應根據規范要求,在乙字管的上部設檢查口以便于檢修;當設計無要求時,應按施工及驗收規范規 定,在連接2個及2個以上大便器或3個及3個以上衛生器具的污水橫管設置清掃口,在轉角小于135度的污水橫管上,設置檢查口或清掃口;排水管道安裝時, 埋地排出管與立管暫不連接,在立管檢查口管插端用托板或其他方法支牢,并及時補好立管穿二層的樓板洞,待確認立管固定可靠后,拆除臨時支撐物,此管口應盡 量避免土建施工時作為臨時污水排出口。在土建裝修基本結束后,給水明敷支管安裝前,對底層及二層以上管道作灌水試驗檢查,證實各管段暢通,然后用直通套(管)筒將檢查口管與底層排出管連接。
2、管道滲漏問題的預防和處理
管道滲漏問題也是給排水管道施工常見的問題,產生這一問題的原因也比較多,對這一問題的預防和處理是給排水施工最關注的核心環節,對管道系統嚴密性的嚴格要求貫穿于整個施工過程中。
產生的原因:管 道滲漏的問題可以從材料、施工操作二方面來分析。材料方面:材料方面的原因包括:管材和管件的強度不合格;管道和管件有砂眼;管道安裝后被人為損壞。這些 情況作者都接觸過,質量問題較多的是鍍鋅鋼管的彎頭,這些劣質彎頭的問題主要是外弧處的壁厚過薄或有砂眼,肉眼一般很難發現。塑料管材原材料的質量一般很 好,出現滲漏的原因一般是安裝后被其他工種施工人員作業時損壞造成。施工操作方面:施工方面的原因包括:鍍鋅鋼管的螺紋加工不合格;管道接口連接不嚴密。這些也是常見的原因。排水管道接口出現滲漏的情況很少,出現這種問題的原因大都是施工馬虎,管道連接時忘記涂膠水或插入深度不夠。入深度標記,這樣容易控 制且便于檢查。
預防措施和處理方法:嚴 格控制采購過程,仔細檢查。對于各批次的管材、管件的使用情況做好記錄,一旦發現問題及時更換。對于PPR管材安裝,應對其的伸縮性采取措施進行預防。可 利用的技術措施有:非直埋管道敷設時,應考慮解決管道熱脹冷縮變形的技術措施。應盡量利用管道折角自由臂補償管道的伸縮;當管道不能利用折角作自然補償 時,應采用其他類型補償措施。水平干管與水平支管連接、水平干管與立管連接、立管和每層支管連接,應有管道伸縮時相互不受影響的補償措施。布置橫管或立管 時應充分利用建筑空間,以“U”形管道做變形補償。出現滲漏問題,需要尋找漏水點,找到漏水點后分析原因。然后,采取相關措施進行處理:更換不合格的管 材、管件;施工操作不合格的一律返工,重新制作安裝;由于熱脹冷縮造成的PPR管材,截去一段管道采取上述的技術措施進行整改(感謝關注機電天下)。
3、閥門的選擇和安裝中問題和預防措施
產生原因:閥門類型選擇不當:閥型與管道系統功能及壓力不匹配,閘閥與截止閥混用,蝶閥與球閥混用,柱塞閥與閘閥混用,明桿閥與暗桿閥混用等,給管道運行和維修帶來不良后果。閥門安裝不利于操作和維修。止回閥安裝位置不當等問題。
預防處理措施:安裝時應考慮操作和維修空間,注意安裝高度和手柄朝向;又如兩個閥門直接連接時,中間缺少穿入螺栓的間隙,應在二閥間增設短管等止回閥必須按指示箭頭安裝。高位水箱出水管的止回閥,應在距水箱底≥1m處水平安裝,以利止回閥正確動作,或采用低阻力止回閥。
4、噪音問題產生原因及處理方法
產生原因:給 水管道壓力超過0.3~0.4MPa且管徑≤20mm及管路較長時,管道會產生嘯叫和振動,這主要由高速水流動力與管道系統產生共振所致。排水管道噪音問 題:排水管的水流呈不充盈和重力流狀態,噪音難免,且受管道材質影響。試驗資料表明,DN100管當流量為2.7L/s時鑄鐵管噪音值為 46.5dB,PVC-U管噪音值為58dB,故在要求安靜的高檔房間,宜選用柔性連接鑄鐵管。新產品芯層發泡隔音PSP管,隔音效果好,價格略貴,也可 選用。
預防處理措施:綜合防治措施有適當加大管徑、采用曲撓橡膠接頭、支架與管道接觸處加橡膠墊以及加裝減壓閥等。但注意減壓閥本身也有噪音,要經反復調試,使噪音減至最小。