第一篇:市政道路工程工作總結(jié)
年度市政公路項(xiàng)目工作總結(jié)
****年是****建筑安裝有限公司在市政公路項(xiàng)目建設(shè)方面取得可喜成績的一年。在****集團(tuán)和公司各級(jí)領(lǐng)導(dǎo)的正確領(lǐng)導(dǎo)和親切關(guān)懷下,市政公路項(xiàng)目緊緊圍繞公司全局發(fā)展戰(zhàn)略,嚴(yán)格按照公司市政項(xiàng)目建設(shè)“高標(biāo)準(zhǔn)、嚴(yán)要求、重細(xì)節(jié)”的管理理念,積極轉(zhuǎn)變思想觀念,端正工作態(tài)度,創(chuàng)新工作思路,圍繞項(xiàng)目年度工作計(jì)劃,狠抓管理形成合力,統(tǒng)籌協(xié)調(diào)穩(wěn)中求進(jìn),著眼發(fā)展打好基礎(chǔ),以高度的責(zé)任心和使命感做好項(xiàng)目管理工作,克服種種困難加快項(xiàng)目進(jìn)展,積極豎立****建筑公司的良好形象。現(xiàn)將一年來市政公路項(xiàng)目建設(shè)情況和明年的工作計(jì)劃匯報(bào)如下:
一、2013年完成的主要工作
2013年市政公路項(xiàng)目在建工程四個(gè),即******市政工程、***一級(jí)公路(三標(biāo)段)、***路市政工程和****路三期市政工程。***一級(jí)公路(三標(biāo)段)于****年**月*日通過專家組竣工驗(yàn)收,****市政工程項(xiàng)目現(xiàn)已進(jìn)入收尾階段,預(yù)計(jì)***年初竣工,東城路城市主干道為201*年元月份新開工項(xiàng)目,預(yù)計(jì)201*年7月竣工,城鄉(xiāng)路三期城市主干道于8月19日舉行開儀式,到目前為止,僅完成征地工作,房屋拆遷、高壓鐵塔遷移仍未啟動(dòng),工程施工還沒有正常展開。
**一級(jí)公路三標(biāo)段路線全長6.0Km,雙向六車道,工程包括路基、路面、防護(hù)等工程,完成總工作量*****萬元,其中201*年完成**00萬元;****園市政道路及場(chǎng)坪工程施工面積約35萬平方米,截止12月底已完成總工作量10500萬元,其中2013年完成6500萬元;東城路線路全長2.657Km,工程包括路基、路面、綠化及市政綜合管溝工程,現(xiàn)已完成路基土石方118萬立方米,完成雨、污排水管網(wǎng)5220米,完成工作量3000萬元。三個(gè)項(xiàng)目均嚴(yán)格按照合同約定完成各項(xiàng)施工任務(wù),全年市政公路項(xiàng)目累計(jì)完成工作量14700萬元,沒有出現(xiàn)非正常的工期延誤,施工質(zhì)量能嚴(yán)格執(zhí)行國家現(xiàn)行施工技術(shù)規(guī)范要求,工程質(zhì)量全部合格,沒有出現(xiàn)質(zhì)量安全事故。
為確保市政公路工程各項(xiàng)管理目標(biāo)的實(shí)現(xiàn),我們主要采取了以下措施,確保工程建設(shè)的穩(wěn)步推進(jìn):
1、以人為本,持續(xù)改進(jìn),積極創(chuàng)新項(xiàng)目管理模式
科技興企,人才強(qiáng)企。以人才的培養(yǎng)和引進(jìn)作為做好工程首要條件,在項(xiàng)目管理過程中,根據(jù)市政公路施工戰(zhàn)線長、管理協(xié)調(diào)難度大、點(diǎn)多面廣的特點(diǎn),積極探索創(chuàng)新管理模式,為項(xiàng)目的順利推進(jìn)起到良好促進(jìn)作用。
(1)從狠抓項(xiàng)目內(nèi)部管理入手加強(qiáng)隊(duì)伍建設(shè)。根據(jù)各項(xiàng)目部工地的施工特點(diǎn)和現(xiàn)場(chǎng)管理的需要,及時(shí)充實(shí)了施工技術(shù)管理人員,確保施工技術(shù)管理人員的配置符合工程建設(shè)的實(shí)際需要。積極關(guān)心和改善員工的食宿條件,努力為員工創(chuàng)造良好的工作環(huán)境,豐富員工的業(yè)余文化生活,提高員工的滿意度;加強(qiáng)對(duì)參建人員進(jìn)行技能培訓(xùn),提高員工的現(xiàn)場(chǎng)管理能力和專業(yè)技能水平,增強(qiáng)員工的團(tuán)隊(duì)意識(shí)和集體榮譽(yù)感,促進(jìn)員工的大局意識(shí)和服務(wù)意識(shí),有效地發(fā)揮員工的凝聚力和創(chuàng)新能力。
(2)加強(qiáng)對(duì)施工勞務(wù)班組的調(diào)配,適時(shí)增加勞務(wù)班組和勞務(wù)人員,通過引進(jìn)競(jìng)爭(zhēng)機(jī)制,充分發(fā)揮勞務(wù)班組的積極性和主動(dòng)性。根據(jù)施工現(xiàn)場(chǎng)的實(shí)際需要,要求勞務(wù)人員中技術(shù)工種占有一定的比例。加強(qiáng)對(duì)勞務(wù)班組的技能培訓(xùn)和職業(yè)健康教育,提高勞務(wù)班組的整體素質(zhì),切實(shí)提高勞動(dòng)效率。
(3)不斷加強(qiáng)自身建設(shè),項(xiàng)目負(fù)責(zé)人帶頭執(zhí)行公司的各項(xiàng)管理規(guī)定,做到身體力行,率先垂范,要求別人做到的自己先做到,要求別人不做的,自己先不做。在施工管理過程中,項(xiàng)目負(fù)責(zé)人經(jīng)常深入各項(xiàng)目施工現(xiàn)場(chǎng)督促指導(dǎo)施工,研究制定關(guān)鍵部位重要工序的施工方案,在施工一線解決施工中出現(xiàn)的各種問題,在項(xiàng)目部起到很好的模范帶頭作用和示范引領(lǐng)作用。通過創(chuàng)新項(xiàng)目管理模式,不僅保障工程建設(shè)的正常有序進(jìn)行,而且,大大提高了員工的工作效率,提高了設(shè)備的利用效益,降低了工程的施工成本,為企業(yè)創(chuàng)造較好的經(jīng)濟(jì)效益打下了良好的基礎(chǔ)。
2、精心組織,精細(xì)施工,全面提升工程建設(shè)質(zhì)量
質(zhì)量是企業(yè)的生命,質(zhì)量是企業(yè)的立足之本。主要采取以下質(zhì)量管理措施:
(1)成立了以項(xiàng)目經(jīng)理為組長的質(zhì)量管理小組,加大了質(zhì)量管理力度,健全了自上而下的質(zhì)量管理體系,完善了內(nèi)部質(zhì)量事故責(zé)任追究制度,簽定質(zhì)量責(zé)任狀等多種措施,不斷提高全體員工質(zhì)量責(zé)任認(rèn)識(shí)。施工過程中,做到“事先預(yù)控,過程把關(guān),事后檢查”,對(duì)于易出現(xiàn)質(zhì)量通病的工序和環(huán)節(jié)采取預(yù)控措施,防患于未然。做到施工現(xiàn)場(chǎng)不停止,施工人員不離崗,全面加強(qiáng)過程管理,使整個(gè)工程質(zhì)量都處在受控狀態(tài)。
(2)各分項(xiàng)工程開工前,嚴(yán)格實(shí)行的班前技術(shù)交底制,并在技術(shù)交底會(huì)上通報(bào)本工序的質(zhì)量預(yù)控措施和質(zhì)量控制點(diǎn),要充分體現(xiàn)質(zhì)量控制以動(dòng)控制為主的原則。(3)認(rèn)真執(zhí)行質(zhì)量檢查“三檢制”。進(jìn)場(chǎng)的材料經(jīng)檢查和試驗(yàn)必須合格,隱蔽工程必須通過業(yè)主、監(jiān)理、施工三方共同驗(yàn)收合格方可隱蔽。嚴(yán)格執(zhí)行試驗(yàn)段樣板引路制度,以試驗(yàn)路段取得的成功經(jīng)驗(yàn)在工地進(jìn)行推廣,要求所有施工人員和勞務(wù)班組人員觀摩學(xué)習(xí),均照此施工。
通過采取以上措施,一年來,工程沒有出現(xiàn)較大的質(zhì)量問題,沒有出現(xiàn)停工、返工造成經(jīng)濟(jì)損失等現(xiàn)象,確保了每道工序質(zhì)量一次性驗(yàn)收合格。各項(xiàng)目部主要施工技術(shù)人員均明確了職責(zé),做到分工協(xié)作,各負(fù)其責(zé),積極推行全面質(zhì)量管理,確保工程質(zhì)量有新的提高和突破。物流園市政工程建設(shè)接受宜昌市質(zhì)監(jiān)、安全部門的兩次大檢查,受到各級(jí)領(lǐng)導(dǎo)的好評(píng)。小鴉路(三標(biāo)段)于11月5日一次性通專家組驗(yàn)收合格。
3、科學(xué)管理,統(tǒng)籌協(xié)調(diào),確保按期完成施工任務(wù) 根據(jù)業(yè)主下達(dá)的總體進(jìn)度計(jì)劃要求,制定了切實(shí)可行的施工方案和進(jìn)度計(jì)劃。為確保任務(wù)目標(biāo)的實(shí)現(xiàn),主要采取了以下措施:(1)根據(jù)工程的施工特點(diǎn),項(xiàng)目部采取平型作業(yè)施工,對(duì)業(yè)主按節(jié)點(diǎn)交給我們的施工任務(wù),項(xiàng)目部加大人員和設(shè)備的投入,盡量把施工任務(wù)向前推進(jìn)。
(2)加大原材料采購和儲(chǔ)備工作,堅(jiān)決杜絕浪費(fèi)材料和偷工減料現(xiàn)象。(3)項(xiàng)目部在保證工程質(zhì)量和施工安全的前提下,抓住重點(diǎn),統(tǒng)籌協(xié)調(diào),盡量增加作業(yè)面,為工程施工創(chuàng)造一切有利條件,全力打好節(jié)點(diǎn)的攻堅(jiān)戰(zhàn),確保按期完成工作目標(biāo)。
4、安全生產(chǎn),防患未然,努力創(chuàng)建和諧平安工地
安全是企業(yè)的生存之本,我們始終把安全放到一切工作的首位。各項(xiàng)目部認(rèn)真落實(shí)公司安全部門下達(dá)的各項(xiàng)安全管理制度和現(xiàn)場(chǎng)整改意見,接受業(yè)主和監(jiān)理下達(dá)的安全指令,始終堅(jiān)持“安全生產(chǎn),預(yù)防為主”的方針。切實(shí)做到安全工作不斷檔,管理不削弱。主要采取了以下安全保障措施:
(1)以創(chuàng)建安全文明工地為目標(biāo),堅(jiān)持管生產(chǎn)必須管安全。項(xiàng)目負(fù)責(zé)人是安全生產(chǎn)第一責(zé)任人,全面部署安全工作,建立安全生產(chǎn)保證體系,制定適合于施工特點(diǎn)的安全管理制度和相應(yīng)的安全措施;加大安全投入,配備各種安全防護(hù)用品;提高員工的安全生產(chǎn)責(zé)任意識(shí)為重中之重,項(xiàng)目部全面落實(shí)安全教育,堅(jiān)持崗前培訓(xùn),安全生產(chǎn)考核,層層落實(shí)安全生產(chǎn)責(zé)任制并簽訂安全生產(chǎn)責(zé)任狀。
(2)定期召開項(xiàng)目部安全生產(chǎn)會(huì)議和勞務(wù)班組安全會(huì)議,積極開展安全生產(chǎn)大檢查,嚴(yán)肅認(rèn)真查處各類安全隱患,做到安全管理規(guī)范化和常態(tài)化,嚴(yán)格控制各類安全事故的發(fā)生。由于安全管理到位,措施有力,全年未發(fā)生重大的安全事故,為工程的施工營造了良好和諧的施工環(huán)境,達(dá)到了預(yù)期安全生產(chǎn)目標(biāo)要求。
二、存在的問題 在總結(jié)成績的同時(shí),我們也認(rèn)識(shí)到自身存在的問題和不足: 要努力提升自身業(yè)務(wù)水平,力求達(dá)到高層次管理要求。克服管理上存在的不足,進(jìn)一步加強(qiáng)對(duì)各項(xiàng)工作的檢查、督促和落實(shí);進(jìn)一步做好與相關(guān)部門的溝通與協(xié)調(diào)。今后,要努力把個(gè)人的本職工作做得精益求精,接受公司全體人員的監(jiān)督與檢查。
三、201*年的工作安排 201*年在建項(xiàng)目的工作安排:
1、做好****園的收尾工程,***園和**路竣工結(jié)算和審計(jì)工作在201*年6月30日以前完成。
2、***路在201*年7月以前全面完工,達(dá)到竣工驗(yàn)收條件。
3、城鄉(xiāng)路在201*年12月以前全面完工,達(dá)到竣工驗(yàn)收條件。201*年除了繼續(xù)做好以上項(xiàng)目的后續(xù)施工以外,還要大力拓展業(yè)務(wù),增強(qiáng)企業(yè)的發(fā)展后勁。要緊緊依托稻花香集團(tuán)企業(yè)的發(fā)展,緊緊抓住宜昌建設(shè)特大城市的機(jī)遇,采取“走出去、請(qǐng)進(jìn)來”的方針,搶抓項(xiàng)目,抓大項(xiàng)目,力爭(zhēng)在項(xiàng)目建設(shè)的數(shù)量、質(zhì)量和經(jīng)濟(jì)效益各方面都有新的突破,在2013年的基礎(chǔ)上再上一個(gè)新臺(tái)階。隨著宜昌城市建設(shè)步伐的加快,建設(shè)特大城市的夢(mèng)想將逐步變成現(xiàn)實(shí)。城市建設(shè)的大發(fā)展給我們帶來了良好的機(jī)遇和廣闊的發(fā)展空間,市政公路項(xiàng)目在公司的業(yè)務(wù)發(fā)展中,將發(fā)揮著越來越重要的作用。面對(duì)機(jī)遇,我們信心百倍,也深感責(zé)任重大;面對(duì)挑戰(zhàn),我們百折不撓,勇于戰(zhàn)勝各種困難和風(fēng)險(xiǎn)。希望各級(jí)領(lǐng)導(dǎo)和公司各部門繼續(xù)大力關(guān)心和支持市政公路項(xiàng)目的工作,我們一定團(tuán)結(jié)一心、攻堅(jiān)克難、奮發(fā)有為,努力把市政公路項(xiàng)目做大做強(qiáng),做出品牌,做出形象。
在今后的工作中,我們要一如既往地做好自己的本職工作,切實(shí)加強(qiáng)自身建設(shè)和執(zhí)行能力建設(shè),以高度的責(zé)任心和緊迫感,推進(jìn)市政公路項(xiàng)目的各項(xiàng)工作有序開展,確保各項(xiàng)施工任務(wù)達(dá)到預(yù)期的目標(biāo)。要居安思危,有預(yù)見性地進(jìn)行統(tǒng)籌謀劃,把不利因素轉(zhuǎn)化為有利因素,借鑒先進(jìn)的項(xiàng)目管理經(jīng)驗(yàn)和同行的科學(xué)管理方法,帶領(lǐng)全體員工,不斷提高工作效率和服務(wù)水平,增強(qiáng)自身的使命感和責(zé)任感,開拓創(chuàng)新、頑強(qiáng)拼搏、艱苦奮斗、扎實(shí)工作,努力把工程質(zhì)量、進(jìn)度、安全等各項(xiàng)工作做好、做扎實(shí),以良好工程形象和較好的經(jīng)濟(jì)效益向公司領(lǐng)導(dǎo)匯報(bào),為實(shí)現(xiàn)公司宏偉的發(fā)展目標(biāo)而努力奮斗!
謝謝大家!
項(xiàng)目負(fù)責(zé)人:
二0一三年十二月二十八日
第二篇:市政道路工程技術(shù)員工作總結(jié)
工作總結(jié)
本人孫富強(qiáng)現(xiàn)任職于青島坤德建設(shè)工程有限公司技術(shù)員,任職期間負(fù)責(zé)如下工程:
膠南市顧家崖頭室外配套工程,本工程主要包括室外雨污管道、熱力、自來水管道,小區(qū)道路、人行道、景觀鋪裝等工程。
膠南市寶山鎮(zhèn)中學(xué)餐廳工程,本工程主體為鋼結(jié)構(gòu)包括室內(nèi)給排水,室內(nèi)裝飾工程及室外鋪裝工程等
目前在施工程為瑯琊臺(tái)度假區(qū)龍橋路綠化工程,道路累計(jì)長度為1000米,包含道路、污水管道、路燈、綠化及景觀鋪裝工程。
在領(lǐng)導(dǎo)和同事們的支持和幫助下,我堅(jiān)持不斷地學(xué)習(xí)理論知識(shí)、總結(jié)工作經(jīng)驗(yàn),加強(qiáng)自身思想修養(yǎng),努力提高綜合素質(zhì),嚴(yán)格遵守各項(xiàng)規(guī)章制度,完成了自己崗位的各項(xiàng)職責(zé)。
具體職責(zé)內(nèi)容如下:
1.在項(xiàng)目總工的指導(dǎo)下,認(rèn)真執(zhí)行相應(yīng)的技術(shù)規(guī)范、規(guī)程和標(biāo)準(zhǔn),協(xié)助主管工程師做好日常技術(shù)工作。
2.熟悉設(shè)計(jì)文件、技術(shù)規(guī)范、施工方法、施工安排等,參加有關(guān)技術(shù)交底與施工組織設(shè)計(jì)、技術(shù)組織措施的編寫工作。3.做好各項(xiàng)技術(shù)準(zhǔn)備工作,并深入工地,進(jìn)行技術(shù)業(yè)務(wù)指導(dǎo)與工程質(zhì)量、進(jìn)度檢查,做好詳細(xì)的技術(shù)交底,及時(shí)解決施工中存在的技術(shù)問題。
4.在項(xiàng)目總工的指導(dǎo)下,溝通設(shè)計(jì)人員、現(xiàn)場(chǎng)監(jiān)理人員、建設(shè)單位人員,對(duì)項(xiàng)目工程的技術(shù)管理及執(zhí)行情況,進(jìn)行解釋與改進(jìn)工作。
5.負(fù)責(zé)日常收集、整理并編寫技術(shù)總結(jié)和編制竣工文件的有關(guān)原始資料、基礎(chǔ)資料。
6.參加隱蔽工程檢查及交工驗(yàn)收。負(fù)責(zé)工程檔案中各項(xiàng)技術(shù)資料的簽證、收集、整理工作,做好施工日志。
7.做好本崗位記錄的收集、整理、填報(bào)、歸檔工作,確保技術(shù)文件的質(zhì)量,并對(duì)技術(shù)文件和資料的有效性、真實(shí)性負(fù)責(zé)。為做好一名技術(shù)管理人員,在按照以上職責(zé)內(nèi)容工作的同時(shí),還應(yīng)該在技術(shù)管理及施工過程管理中重點(diǎn)加強(qiáng):
在相關(guān)技術(shù)管理方面:
一是對(duì)重要受控文件要做到及時(shí)學(xué)習(xí)、執(zhí)行、整理及歸檔; 二是對(duì)各項(xiàng)規(guī)范應(yīng)充分的掌握,通過上網(wǎng)及時(shí)了解該規(guī)范的動(dòng)態(tài),對(duì)于新規(guī)范主要學(xué)習(xí)摒棄了哪些內(nèi)容,增加了哪些知識(shí),改動(dòng)了哪些要求;
三是參與圖紙會(huì)審,將設(shè)計(jì)圖紙的不足、不合理、難施工,有矛盾等地方用文字以問題的形式提出來,約定會(huì)審時(shí)間,逐條問題進(jìn)行研究,之后設(shè)計(jì)人員進(jìn)行一一答復(fù),形成文字記錄。
在施工過程管理方面:
一是隨同主任工程師對(duì)施工圖進(jìn)行圖紙交底工作,同時(shí)編制符合要求并切實(shí)可行的施工方案;
二是編寫技術(shù)交底單、進(jìn)行交底,并在施工期間檢查是否按照方案及交底單執(zhí)行;
三是對(duì)施工現(xiàn)場(chǎng)進(jìn)行檢查規(guī)范、標(biāo)準(zhǔn)的執(zhí)行情況,發(fā)現(xiàn)問題提出整改并跟蹤整改落實(shí)情況;
對(duì)于施工出現(xiàn)的技術(shù)難題,我的解決方法一般首先先通過查閱有關(guān)的技術(shù)規(guī)范、規(guī)程,看對(duì)此類技術(shù)問題是如何要求規(guī)定的,尋找解決辦法,再通過上網(wǎng)查閱此類技術(shù)難題,借鑒他們的解決辦法,尋找自己的解決辦法,再有就是詢問有經(jīng)驗(yàn)的技術(shù)員,施工員,和同事在一起進(jìn)行商討,確定最終的解決辦法。
在對(duì)外關(guān)系協(xié)調(diào)方面的問題上,應(yīng)根據(jù)其特點(diǎn)和主要矛盾,動(dòng)態(tài)地、有針對(duì)性地通過組織協(xié)調(diào),及時(shí)溝通,排除障礙,化解矛盾,充分調(diào)動(dòng)有關(guān)人員的積極性,發(fā)揮各方面的能動(dòng)作用,協(xié)同努力,提高項(xiàng)目組織的運(yùn)轉(zhuǎn)效率,以保證項(xiàng)目施工活動(dòng)順利進(jìn)行,更好地實(shí)現(xiàn)項(xiàng)目總目標(biāo)。
最后,我將在業(yè)務(wù)知識(shí)方面繼續(xù)加強(qiáng)學(xué)習(xí),提高自身水平,緊跟時(shí)代的腳步,拓寬思路的同時(shí)掌握對(duì)新技術(shù)的運(yùn)用,提高思想認(rèn)識(shí),開拓視野。通過認(rèn)真細(xì)致的努力工作,爭(zhēng)取更好的完成領(lǐng)導(dǎo)安排的任務(wù),努力為城市市政基礎(chǔ)設(shè)施建設(shè)作出貢獻(xiàn)。
孫富強(qiáng)
2015年 9月
第三篇:市政道路工程技術(shù)員工作總結(jié)
技術(shù)員工作總結(jié)
本人xxx,xx歲,xx年xx月畢業(yè)于xxxxx,xx年繼續(xù)教育取得xxx本科學(xué)歷,任職于xx公司技術(shù)員,現(xiàn)已工作7年。
目前本項(xiàng)目部在施工程為xxxx工程,道路累計(jì)長度為3863米,包含道路、雨水、污水、給水、再生水管線工程,現(xiàn)管線工程已完成60%,即將進(jìn)行隨路專業(yè)管線施工。
在領(lǐng)導(dǎo)和同事們的支持和幫助下,我堅(jiān)持不斷地學(xué)習(xí)理論知識(shí)、總結(jié)工作經(jīng)驗(yàn),加強(qiáng)自身思想修養(yǎng),努力提高綜合素質(zhì),嚴(yán)格遵守各項(xiàng)規(guī)章制度,完成了自己崗位的各項(xiàng)職責(zé)。
具體職責(zé)內(nèi)容如下:
1.在項(xiàng)目總工的指導(dǎo)下,認(rèn)真執(zhí)行相應(yīng)的技術(shù)規(guī)范、規(guī)程和標(biāo)準(zhǔn),協(xié)助主管工程師做好日常技術(shù)工作。2.熟悉設(shè)計(jì)文件、技術(shù)規(guī)范、施工方法、施工安排等,參加有關(guān)技術(shù)交底與施工組織設(shè)計(jì)、技術(shù)組織措施的編寫工作。
3.做好各項(xiàng)技術(shù)準(zhǔn)備工作,并深入工地,進(jìn)行技術(shù)業(yè)務(wù)指導(dǎo)與工程質(zhì)量、進(jìn)度檢查,參加交班會(huì),做好詳細(xì)的技術(shù)交底,及時(shí)解決施工中存在的技術(shù)問題。4.在項(xiàng)目總工的指導(dǎo)下,溝通設(shè)計(jì)人員、現(xiàn)場(chǎng)監(jiān)理人員、建設(shè)單位人員,對(duì)項(xiàng)目工程的技術(shù)管理及執(zhí)行情況,進(jìn)行解釋與改進(jìn)工作。
5.負(fù)責(zé)日常收集、整理并編寫技術(shù)總結(jié)和編制竣工文件的有關(guān)原始資料、基礎(chǔ)資料。
6.參加隱蔽工程檢查及交工驗(yàn)收。負(fù)責(zé)工程檔案中各項(xiàng)技術(shù)資料的簽證、收集、整理工作,做好施工日志。7.做好本崗位記錄的收集、整理、填報(bào)、歸檔工作,確保技術(shù)文件的質(zhì)量,并對(duì)技術(shù)文件和資料的有效性、真實(shí)性負(fù)責(zé)。
為做好一名技術(shù)管理人員,在按照以上職責(zé)內(nèi)容工作的同時(shí),還應(yīng)該在技術(shù)管理及施工過程管理中重點(diǎn)加強(qiáng):
在相關(guān)技術(shù)管理方面:
一是對(duì)重要受控文件要做到及時(shí)學(xué)習(xí)、執(zhí)行、整理及歸檔;
二是對(duì)各項(xiàng)規(guī)范應(yīng)充分的掌握,通過上網(wǎng)及時(shí)了解該規(guī)范的動(dòng)態(tài),對(duì)于新規(guī)范主要學(xué)習(xí)摒棄了哪些內(nèi)容,增加了哪些知識(shí),改動(dòng)了哪些要求;
三是對(duì)施工現(xiàn)場(chǎng)的布置要做到布局合理,便于施工并能降低工程成本,以及盡可能把臨時(shí)工程與永久工程相結(jié)合,盡量少占耕地,減少投資和節(jié)約用地;
四是參與圖紙會(huì)審,將設(shè)計(jì)圖紙的不足、不合理、難施工,有矛盾等地方用文字以問題的形式提出來,約定會(huì)審時(shí)間,逐條問題進(jìn)行研究,之后設(shè)計(jì)人員進(jìn)行一一答復(fù),形成文字記錄。
在施工過程管理方面:
一是隨同主任工程師對(duì)施工圖進(jìn)行圖紙交底工作,同時(shí)編制符合要求并切實(shí)可行的施工方案;
二是編寫技術(shù)交底單、進(jìn)行交底,并在施工期間檢查是否按照方案及交底單執(zhí)行;
三是對(duì)施工現(xiàn)場(chǎng)進(jìn)行檢查規(guī)范、標(biāo)準(zhǔn)的執(zhí)行情況,發(fā)現(xiàn)問題提出整改并跟蹤整改落實(shí)情況;
四是對(duì)經(jīng)專家論證通過的方案的執(zhí)行情況進(jìn)行檢查,尤其對(duì)于專家提出需修改調(diào)整的技術(shù)要求等問題,經(jīng)方案修改調(diào)整完善并通過后,現(xiàn)場(chǎng)的執(zhí)行情況進(jìn)行重點(diǎn)檢查,發(fā)現(xiàn)問題及時(shí)上報(bào)。
另外,對(duì)于施工技術(shù)難題的解決、工程變更管理的方式方法方面,我對(duì)其總結(jié)一些心得體會(huì)如下:
對(duì)于施工出現(xiàn)的技術(shù)難題,我的解決方法一般首先先通過查閱有關(guān)的技術(shù)規(guī)范、規(guī)程,看對(duì)此類技術(shù)問題是如何要求規(guī)定的,尋找解決辦法,再通過上網(wǎng)查閱此類技術(shù)難題,借鑒他們的解決辦法,尋找自己的解決辦法,再有就是詢問有經(jīng)驗(yàn)的技術(shù)員,施工員,和同事在一起進(jìn)行商討,確定最終的解決辦法。
對(duì)于如何做好工程變更的管理,本人感想如下內(nèi)容需重點(diǎn)加強(qiáng)管理: 一是變更項(xiàng)目的確定過程;變更的分類,收集原始資料,做好超前準(zhǔn)備,積極與業(yè)主、監(jiān)理工程師溝通,尋找最佳變更方案。二是變更費(fèi)用的確定過程;進(jìn)行單價(jià)分析,確定變更單價(jià)和工程量。三是變更臺(tái)賬的管理等方面
我們應(yīng)重視工程變更對(duì)工程造價(jià)管理的影響,加強(qiáng)工程變更的研究與管理,做好變更管理的基礎(chǔ)工作;另外要求變更管理人員要有高度的責(zé)任心、耐心和細(xì)心謹(jǐn)慎的工作態(tài)度,時(shí)刻本著對(duì)工作負(fù)責(zé)、對(duì)項(xiàng)目負(fù)責(zé)、對(duì)企業(yè)負(fù)責(zé)的立場(chǎng),對(duì)任何一個(gè)可能發(fā)生變更的項(xiàng)目,都認(rèn)真對(duì)待、測(cè)算分析,盡可能合理有效地確定變更費(fèi)用。
在對(duì)外關(guān)系協(xié)調(diào)方面的問題上,應(yīng)根據(jù)其特點(diǎn)和主要矛盾,動(dòng)態(tài)地、有針對(duì)性地通過組織協(xié)調(diào),及時(shí)溝通,排除障礙,化解矛盾,充分調(diào)動(dòng)有關(guān)人員的積極性,發(fā)揮各方面的能動(dòng)作用,協(xié)同努力,提高項(xiàng)目組織的運(yùn)轉(zhuǎn)效率,以保證項(xiàng)目施工活動(dòng)順利進(jìn)行,更好地實(shí)現(xiàn)項(xiàng)目總目標(biāo)。
例如:由于本工程的特殊性,3月份進(jìn)場(chǎng)后,因施工圖紙嚴(yán)重滯后,造成了主要管線開工晚的情況發(fā)生,為挽回?fù)p失的時(shí)間,經(jīng)項(xiàng)目部領(lǐng)導(dǎo)協(xié)調(diào),我部門多次與設(shè)計(jì)人進(jìn)行溝通,對(duì)存有異議的部分進(jìn)行研究調(diào)整,為了即保工期又保質(zhì)量,本著合規(guī)、合理、合要求的宗旨,通過與設(shè)計(jì)反復(fù)溝通,共同努力下,積極地挽回了部分寶貴工期,適當(dāng)?shù)木徑饬斯て趬毫ΑW詈螅覍⒃跇I(yè)務(wù)知識(shí)方面繼續(xù)加強(qiáng)學(xué)習(xí),提高自身水平,緊跟時(shí)代的腳步,拓寬思路的同時(shí)掌握對(duì)新技術(shù)的運(yùn)用,提高思想認(rèn)識(shí),開拓視野。通過認(rèn)真細(xì)致的努力工作,爭(zhēng)取更好的完成領(lǐng)導(dǎo)安排的任務(wù),努力為北京市政基礎(chǔ)設(shè)施建設(shè)作出貢獻(xiàn)。
xxx 2012-x-xx
第四篇:市政道路工程監(jiān)理工作總結(jié)-
市政工程
監(jiān)理工作總結(jié)
編制:________________
審核:________________
審批:_______________
工程管理有限公司
2018年9月
目
錄
一、工程概況 ························································································ 1
二、監(jiān)理組織機(jī)構(gòu)和設(shè)施投入 ··································································· 2
三、合同和信息管理 ··············································································· 2
四、施工概況及對(duì)承包商的評(píng)價(jià)意見 ·························································· 2
五、工程質(zhì)量控制及評(píng)價(jià)意見 ··································································· 2
(一)施工準(zhǔn)備階段的質(zhì)量控制 ··························································· 2
(二)施工階段質(zhì)量控制 ···································································· 3
(三)資金投資控制 ·········································································· 4
(四)竣工驗(yàn)收階段質(zhì)量控制 ······························································ 4
六、施工階段的工程進(jìn)度控制 ··································································· 4
七、施工階段工程投資控制 ······································································ 5
八、安全、文明施工控制 ········································································· 5
九、體會(huì)、經(jīng)驗(yàn)、建議 ············································································ 5
道路工程 監(jiān)理工作總結(jié)
一、工程概況
工程名稱:
建設(shè)單位:
設(shè)計(jì)單位: 監(jiān)理單位:
施工單位:
工程內(nèi)容:本工程為***雨水管網(wǎng)改造工程,北起**路雨水井Y1-1南至雨水井Y1-22,總長789米。雨水管道為磚砌體矩形管道,現(xiàn)澆鋼筋混凝土底板,預(yù)制鋼筋混凝土蓋板。**路至**路段為3000mm*1000mm、***路至***路段為3000mm*1600mm。管道鋪設(shè)位置路面破碎拆除、垃圾外運(yùn)。路面恢復(fù),自上而下為26cm鋼筋混凝土路面面板、15cm石灰粉煤灰碎石、15cm石灰粉煤灰土、15cm石灰土、回填素土壓實(shí),壓實(shí)系數(shù)0.95。雨收水井恢復(fù),新建雨水溝與舊雨水管道接口。
計(jì)劃工期: 質(zhì)量目標(biāo): 工程投資:
/6
參加了對(duì)工程基準(zhǔn)線、坐標(biāo)網(wǎng)、控制樁和水準(zhǔn)點(diǎn)的現(xiàn)場(chǎng)交底,并對(duì)水準(zhǔn)點(diǎn)、控制點(diǎn)進(jìn)行了復(fù)核。檢查了開工條件,如承包商工、料、機(jī)落實(shí)、進(jìn)場(chǎng)情況;水泥、鋼筋、砂、石料及預(yù)制管構(gòu)件、主要外購件的質(zhì)量及有關(guān)復(fù)試資料,對(duì)部分供應(yīng)廠家進(jìn)行了實(shí)地考察,見證了復(fù)試試驗(yàn),構(gòu)配件質(zhì)量滿足設(shè)計(jì)及規(guī)范要求,適用于本工程。
召開首次工地會(huì)議,明確了施工過程中業(yè)主、承包商、監(jiān)理方三方各自的職責(zé)和監(jiān)理工作管理辦法。編制了詳細(xì)的《監(jiān)理規(guī)劃》、《監(jiān)理細(xì)則》,為我們開展監(jiān)理工作打下了基礎(chǔ)。
(二)施工階段質(zhì)量控制
在施工中要求承包商建立起完善的質(zhì)量檢測(cè)體系,必須在自檢合格的基礎(chǔ)上通知相關(guān)主體單位驗(yàn)收,經(jīng)監(jiān)理簽認(rèn)后,方能進(jìn)入下道工序施工。
督促施工單位做好施工水準(zhǔn)點(diǎn)、控制點(diǎn)、基準(zhǔn)線的測(cè)量、復(fù)核管道中心定位、復(fù)核工作,并檢查其有關(guān)記錄,在施工單位上報(bào)復(fù)測(cè)資料的基礎(chǔ)上,對(duì)臨時(shí)水準(zhǔn)點(diǎn)等進(jìn)行了復(fù)核,其結(jié)果均在誤差范圍內(nèi)。同時(shí),多次抽檢了管道中線的控制點(diǎn)、中心樁、檢查井位置,確保其準(zhǔn)確性。
在溝槽開挖工序中,檢查了承包商溝槽開挖坡度、安全,溝槽排水、支撐措施是否落實(shí),重點(diǎn)控制溝槽不得受水浸泡,防止槽底土體擾動(dòng)和超挖。
會(huì)同業(yè)主、地勘、質(zhì)檢、施工等五方主體對(duì)溝槽進(jìn)行驗(yàn)收,驗(yàn)收過程各數(shù)據(jù)我方均做詳細(xì)記錄,在抽檢墊層、平基的厚度及高程無誤后,才允許施工單位進(jìn)入管道安裝工序的施工工作。
管道安裝工作重點(diǎn)檢查管底坡度是否倒流水,管道中心線位置是否符合設(shè)計(jì)要求,并對(duì)管內(nèi)底高程進(jìn)行檢測(cè),同時(shí),隨機(jī)抽取了以上各道工序的混凝土質(zhì)量,見證了試塊試壓,全部達(dá)到設(shè)計(jì)要求。
/6
工程進(jìn)度款支付憑證。
七、施工階段工程投資控制
本工程投資控制的原理是把計(jì)劃投資額作為投資控制的目標(biāo)值,在工程施工過程中定期進(jìn)行投資實(shí)際值與目標(biāo)值比較,通過比較發(fā)現(xiàn)并找出實(shí)際支出額與投資控制目標(biāo)值的偏差,然后分析產(chǎn)生偏差的原因,并采取有效措施加以控制,以保證投資控制目標(biāo)的實(shí)現(xiàn)。首先,我方熟悉圖紙、設(shè)計(jì)要求、標(biāo)底標(biāo)書,分析合同價(jià)構(gòu)成因素,明確工程費(fèi)用最易突破的部分和環(huán)節(jié),從而明確投資控制的重點(diǎn)。并審查承包商提交的工程預(yù)算,定期、不定期進(jìn)行工程費(fèi)用超支分析,并提出控制工程費(fèi)用突破的方案和措施。認(rèn)真、慎重對(duì)待工程變更、設(shè)計(jì)修改,嚴(yán)格經(jīng)費(fèi)簽證,及時(shí)對(duì)完工工程量進(jìn)行計(jì)量,及時(shí)簽證支付進(jìn)度款。
八、安全、文明施工控制
安全、文明施工是保證工程能否順利地在額定工期內(nèi)按時(shí)、保質(zhì)完成的重要條件。我方對(duì)此緊抓不懈,督促承包商在施工中認(rèn)真貫徹“安全第一,預(yù)防為主”和堅(jiān)持“管生產(chǎn)必須管安全”的原則。我方督促參加施工的人員必須接受安全技術(shù)教育,熟知和遵守本工種的各項(xiàng)安全技術(shù)操作規(guī)程,并要求定期進(jìn)行安全技術(shù)考核,對(duì)特殊工種操作人員,我方檢查其特殊工種合格證后,才能上崗作業(yè)。
操作人員上崗前,要求必須按照規(guī)定穿戴防護(hù)用品,督促施工負(fù)責(zé)人和安全檢查員隨時(shí)檢查勞動(dòng)防護(hù)用品的穿戴情況,并組織人員定期檢查和驗(yàn)收施工所用的各種機(jī)具設(shè)備、勞動(dòng)保護(hù)用品和電器設(shè)備等,保證其處于完好狀態(tài)。
九、體會(huì)、經(jīng)驗(yàn)、建議
1、業(yè)主的支持是保證工程順利完成的基礎(chǔ):在整個(gè)施工過程中業(yè)主領(lǐng)導(dǎo)對(duì)監(jiān)理方在各方面都給予了大力的支持和協(xié)助,積極支持監(jiān)理方的各項(xiàng)管理措施和監(jiān)理手段,為工程的順利完成提供了保證。
2、協(xié)調(diào)、溝通的重要性:在項(xiàng)目實(shí)施過程中,有很多的協(xié)調(diào)溝通
/6
更好地把監(jiān)理
第五篇:市政道路工程監(jiān)理工作總結(jié)(樣本)
道路整修工程
監(jiān)理工作總結(jié)
編制:
審核:
日期:
沈陽市建設(shè)工程項(xiàng)目管理中心
目 錄
一、工程概況 ················································································ 1
二、監(jiān)理組織機(jī)構(gòu)和設(shè)施投入 ···················································· 1
三、監(jiān)理合同履行情況 ································································ 1
(一)質(zhì)量控制 ····································································· 2
(二)投資控制 ····································································· 5
(三)進(jìn)度控制: ································································· 6
(四)合同管理 ····································································· 6
(五)信息管理 ····································································· 7
(六)組織協(xié)調(diào) ····································································· 7
四、監(jiān)理工作成效 ········································································ 8
五、小結(jié) ······················································································· 8
一、工程概況
工程名稱: 道路整修工程 建設(shè)單位:*****公司 建設(shè)地址:****** 監(jiān)理單位:*****監(jiān)理公司 質(zhì)量目標(biāo):合格
二、監(jiān)理組織機(jī)構(gòu)和設(shè)施投入
本工程成立由 任總監(jiān)理工程師,任專業(yè)監(jiān)理工程師,任專業(yè)監(jiān)理工程師的組織機(jī)構(gòu),總監(jiān)受公司委托和業(yè)主授權(quán)全面負(fù)責(zé)本工程的監(jiān)理工作,總監(jiān)理工程師、專業(yè)監(jiān)理工程師行使各自的職責(zé)。
根據(jù)本工程特點(diǎn),為了便于更好地完成監(jiān)理工作,特自備全站儀、水準(zhǔn)儀各一臺(tái),電腦一套,打印機(jī)一臺(tái)及其他檢測(cè)工具等,從開展監(jiān)理工作中已證實(shí)可以滿足需要。
三、監(jiān)理合同履行情況
根據(jù)監(jiān)理合同委托監(jiān)理的范圍和要求,監(jiān)理方受業(yè)主的委托,對(duì)本工程施工階段和保修階段實(shí)行工程監(jiān)理,本監(jiān)理單位在與業(yè)主商簽了本工程的監(jiān)理合同后,根據(jù)工程項(xiàng)目實(shí)施建設(shè)監(jiān)理的程序,成立項(xiàng)目監(jiān)理組織,向業(yè)主提交了本工程的監(jiān)理規(guī)劃,按照監(jiān)理規(guī)劃實(shí)施本工程施工階段的建設(shè)監(jiān)理工作。
對(duì)在實(shí)施建設(shè)監(jiān)理的過程中,本項(xiàng)目監(jiān)理組織按照國家的有關(guān)規(guī)定,遵循公正、獨(dú)立自主的原則;權(quán)責(zé)一致的原則;嚴(yán)格監(jiān)理、熱情服務(wù)的原則;綜合效益的原則;預(yù)防為主的原則和實(shí)事求是的原則,正確地處理了與業(yè)主、與被監(jiān)理單位和與本工程的相關(guān)單位的關(guān)系。按照建設(shè)監(jiān)理的基本方法體系進(jìn)行了目標(biāo)規(guī)劃、動(dòng)態(tài)控制、組織協(xié)調(diào)、信息管理、合同管理,保持了監(jiān)理過程的服務(wù)性、獨(dú)立性、公正性和科學(xué)性,完成了本工程建設(shè)監(jiān)理的中心任務(wù),即控制工程項(xiàng)目目標(biāo);本監(jiān)理單位派任本工程項(xiàng)目的監(jiān)理工程師,能遵守監(jiān)理工程師的職業(yè)道德和紀(jì)律,能根據(jù)本工程的監(jiān)理合同的業(yè)務(wù)委托范圍和監(jiān)理規(guī)劃確定的職責(zé),較好地行使合同權(quán)利、履行合同義務(wù)和承擔(dān)合同責(zé)任。
(一)質(zhì)量控制
1、在進(jìn)行質(zhì)量控制的過程中,遵循堅(jiān)持質(zhì)量第一原則、堅(jiān)持以人為本控制核心的原則、堅(jiān)持預(yù)防為主的原則、堅(jiān)持質(zhì)量標(biāo)準(zhǔn)的原則和科學(xué)、公正、守法的原則,根據(jù)相關(guān)的國家及政府有關(guān)部門頒布的有關(guān)質(zhì)量管理方面的法律、法規(guī)性文件,工程承包合同文件,施工規(guī)程、本工程有關(guān)的檢驗(yàn)評(píng)定的標(biāo)準(zhǔn)和方法以及設(shè)計(jì)圖紙,確定質(zhì)量控制工作程序;采取事前、事中、事后控制相結(jié)合的質(zhì)量控制方法,對(duì)投入的物質(zhì)資源的質(zhì)量控制、施工過程的質(zhì)量控制和工程產(chǎn)品質(zhì)量的控制,以工序質(zhì)量控制為重點(diǎn)、以保證分項(xiàng)工程質(zhì)量和單位工程質(zhì)量,進(jìn)而確保工程項(xiàng)目質(zhì)量。其中:
事前控制:通過確定質(zhì)量標(biāo)準(zhǔn)、建立質(zhì)量監(jiān)理體系、施工現(xiàn)場(chǎng)的驗(yàn)收、審查審批施工單位資質(zhì),督促承建單位和完善質(zhì)量保
證體系、檢查工程所用的原材料和半成品質(zhì)量、施工機(jī)械質(zhì)量控制、審查審批施工單位的施工組織設(shè)計(jì)、施工方案和開工報(bào)告,組織圖紙會(huì)審和技術(shù)交底的工作,審查施工單位管理人員,特別是項(xiàng)目經(jīng)理、質(zhì)量檢驗(yàn)員、施工員和特殊工種人員的資格,以確保工程投入環(huán)節(jié)的質(zhì)量。
事中控制:通過對(duì)施工過程質(zhì)量的工序控制、工序交接檢查、隱蔽工程檢查驗(yàn)收;中間產(chǎn)品質(zhì)量控制;分項(xiàng)工程質(zhì)量評(píng)定驗(yàn)收;設(shè)計(jì)變更及技術(shù)洽商的處理;監(jiān)理指令、支付的質(zhì)量認(rèn)證工作,以確保工程轉(zhuǎn)換環(huán)節(jié)的質(zhì)量。
事后控制:通過對(duì)單位工程的竣工初驗(yàn)收、項(xiàng)目工程的質(zhì)量評(píng)定、審核竣工資料確保工程項(xiàng)目的質(zhì)量。
2、在進(jìn)行事前控制和事中控制時(shí),始終通過對(duì)影響質(zhì)量的人、材料、機(jī)械、方法和環(huán)境這五大質(zhì)量影響因素的控制,確保工程投入物和產(chǎn)出品的質(zhì)量。其中:對(duì)人的質(zhì)量控制,主要是檢查各類人員的上崗證和制止違章操作;對(duì)材料的質(zhì)量控制主要是對(duì)通過書面檢驗(yàn)進(jìn)場(chǎng)材料的材料質(zhì)量證書、對(duì)進(jìn)場(chǎng)材料進(jìn)行外觀檢驗(yàn)、對(duì)材料抽樣的一般它試驗(yàn)項(xiàng)目進(jìn)行理化檢驗(yàn),把好原材料和半成品的質(zhì)量關(guān);對(duì)施工方法的質(zhì)量控制主要是對(duì)施工采用的技術(shù)方案、工藝流程、組織措施、檢測(cè)手段、施工組織設(shè)計(jì)進(jìn)行控制,重點(diǎn)是對(duì)施工組織設(shè)計(jì)的審批;對(duì)混凝土攪拌機(jī)、砂漿攪拌機(jī)、混凝土提漿機(jī)、壓路機(jī)等施工機(jī)械的質(zhì)量控制主要是對(duì)設(shè)備選型、主要性能參數(shù)和使用操作要求要滿足工程的需要進(jìn)行控制;對(duì)環(huán)境因素的質(zhì)量控制主要是對(duì)工程技術(shù)環(huán)境,工程管理環(huán)境和勞動(dòng)環(huán)境進(jìn)行控制,重點(diǎn)是對(duì)工程的管理環(huán)境中的質(zhì)量保證
體系進(jìn)行控制。
3、質(zhì)量控制的主要方法(1)嚴(yán)格工序質(zhì)量控制
根據(jù)工序的重要性設(shè)置質(zhì)量控制點(diǎn),對(duì)質(zhì)量進(jìn)行預(yù)控和重點(diǎn)控制,在施工過程中監(jiān)理工程師進(jìn)行質(zhì)量監(jiān)控,控制的重點(diǎn)包括:路床分層回填碾壓,路床軟基處理,路床與基層的密實(shí)度,路面混凝土抗壓抗折強(qiáng)度,瀝青路面彎沉;排水溝槽地基承載力,溝槽回填分層夯實(shí)及密實(shí)度;基坑地基承載力,路燈接地電阻等,現(xiàn)場(chǎng)監(jiān)理人員在施工現(xiàn)場(chǎng)實(shí)行旁站控制,隨時(shí)監(jiān)督施工單位在施工過程中可能出現(xiàn)的不合格工序,預(yù)測(cè)施工過程中可能影響工序質(zhì)量的因素,對(duì)各工序進(jìn)行質(zhì)量預(yù)控。同時(shí)重點(diǎn)控制工序活動(dòng)條件和工序活動(dòng)效果,嚴(yán)格按照工序報(bào)檢程序進(jìn)行驗(yàn)收,堅(jiān)持在施工單位報(bào)驗(yàn)的基礎(chǔ)上進(jìn)行工序質(zhì)量驗(yàn)收檢查,經(jīng)驗(yàn)收檢查合格的工序方可進(jìn)行下道工序的施工,對(duì)不合格品嚴(yán)格要求返工處理,保證了工程質(zhì)量目標(biāo)的實(shí)現(xiàn)。
(2)根據(jù)路床碾壓密實(shí)度試驗(yàn)結(jié)果,確定挖方地段預(yù)留碾壓高度,杜絕超挖回填現(xiàn)象。
(3)針對(duì)雨季施工的特點(diǎn),提出調(diào)整二灰基層的粉煤灰、石灰拌和比例,保證基層質(zhì)量。
(4)采用平行檢測(cè)的方法檢測(cè)路床和基層密實(shí)度,平行檢測(cè)混凝土路面的抗折強(qiáng)度,平行檢測(cè)路床、基層面層的高程。
(5)清淤地段采取旁站監(jiān)督,對(duì)清理到原土即要求施工單位停止
清淤工作,避免不必要的浪費(fèi)。
(二)投資控制
項(xiàng)目監(jiān)理部按照招投文件、施工合同、工程施工實(shí)際進(jìn)度、工程質(zhì)量對(duì)所監(jiān)理的各項(xiàng)目進(jìn)行工程款支付控制。
1、按月及時(shí)審批施工單位上報(bào)的工程款月報(bào);
2、及時(shí)統(tǒng)計(jì)已完工工程量,并與投資情況及計(jì)劃相比較;
3、嚴(yán)格審查工程量情況,施工中凡是沒有設(shè)計(jì)變更的簽證,均不予審批。
投資控制主要方法:
1、嚴(yán)把設(shè)計(jì)變更關(guān)。對(duì)工程變更、設(shè)計(jì)修改等事項(xiàng),首先進(jìn)行技術(shù)經(jīng)濟(jì)合理性預(yù)分析,確實(shí)必要時(shí)經(jīng)施工、設(shè)計(jì)、監(jiān)理三方同意并報(bào)送業(yè)主審批后方可實(shí)施,當(dāng)發(fā)現(xiàn)與原投資控制計(jì)劃有較大差異時(shí),及時(shí)向業(yè)主報(bào)告,并與業(yè)主及設(shè)計(jì)人員協(xié)商處理。
2、嚴(yán)格控制費(fèi)用的簽證,凡設(shè)及經(jīng)濟(jì)費(fèi)用支出的簽證認(rèn)真進(jìn)行審核,并要求附上原始依據(jù),同時(shí)會(huì)同業(yè)主核簽后才能生效。
3、做好工程計(jì)量工作本工程合同規(guī)定項(xiàng)目單價(jià)按合同單價(jià)不變,工程量按實(shí)計(jì)量。
4、按照施工合同條款要求進(jìn)行設(shè)計(jì)變更新增項(xiàng)目內(nèi)容單價(jià)審核,共審核單價(jià)項(xiàng)。
(三)進(jìn)度控制: 進(jìn)度控制的主要工作有:
1、組織專業(yè)監(jiān)理工程師審核施工單位提交的施工總進(jìn)度計(jì)劃,使總進(jìn)度計(jì)劃與合同總工期有一定的富余時(shí)間,使各分項(xiàng)工程的施工時(shí)間安排相互之間協(xié)調(diào)一致,同時(shí)符合工期總目標(biāo)的要求。
2、協(xié)助督促承建商實(shí)施進(jìn)度計(jì)劃,隨時(shí)檢查施工進(jìn)度計(jì)劃的關(guān)鍵控制點(diǎn),動(dòng)態(tài)了解進(jìn)度計(jì)劃實(shí)施情況。
3、檢查和審核施工單位提交的月度及周進(jìn)度計(jì)劃,同時(shí)按照周進(jìn)度計(jì)劃嚴(yán)格進(jìn)行進(jìn)度核查,隨時(shí)進(jìn)行進(jìn)度調(diào)整。
4、根據(jù)工程特點(diǎn)設(shè)置節(jié)點(diǎn)重點(diǎn)進(jìn)行控制,為了保證工程總工期目標(biāo)的實(shí)現(xiàn),把總進(jìn)度分為兩個(gè)階段,年春節(jié)前要求施工必須完成排水工程施工及道路路床,下基層的施工,按照此目標(biāo)要求進(jìn)行進(jìn)度的控制。
5、協(xié)助施工單位完善和提高進(jìn)度計(jì)劃管理水平。定期及隨時(shí)進(jìn)行進(jìn)度完成情況檢查對(duì)比,同時(shí)把我們的看法和意見經(jīng)常與施工負(fù)責(zé)人進(jìn)行交換,共同解決存在的進(jìn)度問題。
(四)合同管理
1、認(rèn)真審查施工組織設(shè)計(jì)及施工方案。
2、嚴(yán)格審查分包單位的資質(zhì),使合格的分包商進(jìn)場(chǎng)施工,確保工程的施工質(zhì)量及合同的履行。
3、核定和會(huì)簽設(shè)計(jì)變更和工地洽商變更方面的文件。
4、嚴(yán)格按照合同條款進(jìn)行管理,合同雙方均能認(rèn)真履行合同約定的義務(wù),沒有發(fā)生合同變更、合同糾紛等現(xiàn)象。
5、嚴(yán)格按照監(jiān)理合同條款進(jìn)行工程監(jiān)理,在監(jiān)理活動(dòng)中行使合同權(quán)利、履行合同義務(wù)和承擔(dān)合同責(zé)任。
(五)信息管理
項(xiàng)目監(jiān)理組織對(duì)本工程的勘測(cè)資料設(shè)計(jì)文件、合同文本、會(huì)議紀(jì)要、事故調(diào)查報(bào)告,各種報(bào)表和報(bào)告、施工記錄、往來信函等文件進(jìn)行收集整理、編碼、歸檔,以用于本 資控制、合同管理和信息管理業(yè)務(wù)。在管理過程中,規(guī)定了信息管理流程,制定了各種管理制度,采取了經(jīng)濟(jì)措施、合同措施,促使承建單位及時(shí)地提交有關(guān)資料。并運(yùn)用計(jì)算機(jī)等高科技手段對(duì)各類信息進(jìn)行管理,為工程的質(zhì)量、進(jìn)度、投資情況的評(píng)估和決策提供了可靠的依據(jù)。
(六)組織協(xié)調(diào)
本工程的組織協(xié)調(diào)主要是協(xié)調(diào)業(yè)主、設(shè)計(jì)單位及施工單位等各方的關(guān)系。施工工期要求嚴(yán)格,同時(shí)施工質(zhì)量和投資必須嚴(yán)格控制等,將增加施工現(xiàn)場(chǎng)管理和文明施工的難度。我們通過會(huì)議或洽商等手段,對(duì)施工過程中出現(xiàn)的問題進(jìn)行協(xié)商,及時(shí)解決處理施工中出現(xiàn)的各類問題,保證了施工的順利完成。
(七)安全生產(chǎn)、文明施工管理
安全生產(chǎn)、文明施工是保證工程能否順利地在額定工期內(nèi)按時(shí)、保質(zhì)完成的重要條件。我方對(duì)此緊抓不懈,督促施工單位在施工中認(rèn)真貫徹“安全第一,預(yù)防為主”和堅(jiān)持“管生產(chǎn)必須管安全”的原則。我方督促參加施工的人員必須接受安全技術(shù)教育,熟知和遵守本工種的各項(xiàng)安全技術(shù)操作規(guī)程,并要求定期進(jìn)行安全技術(shù)考核,對(duì)特殊工種操作人員,我方檢查其特殊工種合格證后,才能上崗作業(yè)。
操作人員上崗前,要求必須按照規(guī)定穿戴防護(hù)用品,督促施工負(fù)責(zé)人和安全檢查員隨時(shí)檢查勞動(dòng)防護(hù)用品的穿戴情況,并組織人員定期檢查和驗(yàn)收施工所用的各種機(jī)具設(shè)備、勞動(dòng)保護(hù)用品和電器設(shè)備等,保證其處于完好狀態(tài)。
四、監(jiān)理工作成效
仔細(xì)閱讀施工圖,審查圖紙會(huì)審紀(jì)要,將施工圖中的疑點(diǎn)、難點(diǎn)解決在施工之前。在主要分項(xiàng)、分部或主要工序施工前對(duì)施工方進(jìn)行監(jiān)理交底,使施工方明確在該分項(xiàng)、分部和該主要工序施工中應(yīng)注意的質(zhì)量重點(diǎn)控制內(nèi)容,以便及早采取措施進(jìn)行予控。對(duì)工程的關(guān)鍵和隱蔽部位,采用跟蹤監(jiān)理與旁站監(jiān)理相結(jié)合的手段,使工程施工處于受控狀態(tài)。積極協(xié)助業(yè)主抓好工程質(zhì)量,對(duì)每個(gè)分部、分項(xiàng)的工藝從準(zhǔn)備階段開始控制,環(huán)環(huán)相扣,層層把關(guān),使工程質(zhì)量從整體到每個(gè)分項(xiàng)都符合現(xiàn)行國家公路施工質(zhì)量驗(yàn)收規(guī)范、施工標(biāo)準(zhǔn)、國家公路工程質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)及合同約定。對(duì)文明、安全施工進(jìn)行檢查、監(jiān)督,協(xié)助施工方管理層對(duì)操作人員進(jìn)行安全生產(chǎn)教育,實(shí)現(xiàn)沒無傷亡、無工程質(zhì)量事故。
五、小結(jié)
業(yè)主的支持是保證工程順利完成的基礎(chǔ):在整個(gè)施工過程中業(yè)主領(lǐng)導(dǎo)對(duì)監(jiān)理方在各方面都給予了大力的支持和協(xié)助,積極支持監(jiān)理方的各項(xiàng)管理措施和監(jiān)理手段,為工程的順利完成提供了保證。
協(xié)調(diào)、溝通的重要性:在項(xiàng)目實(shí)施過程中,有很多的協(xié)調(diào)溝通工作要做,一個(gè)成功的監(jiān)理項(xiàng)目部既要嚴(yán)格監(jiān)理工程,也要同承包商建立良好的監(jiān)理和被監(jiān)理的合作關(guān)系,站在不同的角度為了一個(gè)共同目的,做好各自工作,只有這樣才能出色地控制好質(zhì)量、進(jìn)度、投資等各項(xiàng)指標(biāo)。
監(jiān)理項(xiàng)目部自身建設(shè):監(jiān)理工作需要豐富的現(xiàn)場(chǎng)管理經(jīng)驗(yàn)和扎實(shí)的理論水平,綜合素質(zhì)要求很高,要做一個(gè)優(yōu)秀的監(jiān)理工作者,只有取彼之長,補(bǔ)己之短,在工作中不斷提高自身素質(zhì),更好地把監(jiān)理工作做好。
*******監(jiān)理公司