第一篇:電大建筑施工管理實習報告
建筑施工與管理畢業實踐報告
按邯鄲廣播電視大學的畢業實踐安排,我在2014年3月1日到5月30日選擇在***********第一工程分公司壓力容器廠進行實踐學習。壓力容器廠是河北冶金建設集團有限公司第一工程分公司的一個分廠,主要從事壓力容器與非標設備件的制作。我一直在本廠工作,所以在邯鄲電大的要求下我選擇了在自己的崗位上實踐,把我所學到的知識應用到工作實踐中來,以便使我對學到的知識有進一步的認識,再者使自己的工作能更上一層樓。
一、工程概況
公司承接了*******鋼廠煉鋼噴煤改造工程的壓力容器設計制作的任務。現將工程概況介紹如下:*******鋼鐵有限公司煉鐵廠新噴煤技改工程為550m3×2高爐噴煤工程的制粉噴吹車間,壓力容器包括4臺25m3的噴吹罐、1臺40m3的空氣儲罐、1臺40m3的氮氣儲罐、3臺氮氣包、1臺壓縮空氣包共計10臺。廠長把這項工作全權交代給我負責,雖說我一直在做壓力容器,但是我以前就是一個焊工,在焊接方面是沒問題的,其他方面感到很吃力,于是一有空閑時間我就請教我的指導老師,向她學習有關壓力容器制作的相關工作程序與執行標準。
二、實踐內容
壓力容器工作程序相當繁瑣,但不能混亂,質量控制嚴格,均要執行國家制定的相關標準。壓力容器制作程序是:
(一)首先要拿到業主方的制作條件圖,根據條件圖進行重新設計,設計的標準是GB150-2011;
(二)圖紙設計完成后由工藝員與工藝師進行圖紙審核,審核的重點是看設計的壓力容器外形尺寸、接管規格與管口方位、支座方位是否與條件圖相符,看設計執行標準是否是新標準;
(三)圖紙審核沒有問題,根據圖紙所給參數進行排版,工藝編制;
(四)根據工藝卡的排版尺寸訂購材料,做到成本消耗最小化;
(五)材料進場,工藝員把工藝卡交由制作班組長,班組根據工藝卡的排版圖與制作工藝進行下料制作,制作過程有質量檢查員全程跟蹤檢查記錄;
(六)制作完成,出廠前要經過水壓試驗或者是氣密性實驗(有特殊要求的才進行氣密性實驗),壓力大小按圖紙設計要求執行,檢查人員包括質檢員、質檢師、工藝師、材料師、技術監督局駐場人員。檢查合格需要在場所有人員簽字認可,留存檔案;
(七)完善資料,技術監督局報批備案。設備合格證隨設備交由業主存檔。這就是壓力容器的制作的全過程。
這次壓力容器的制做,我從到尾全程跟蹤,從圖紙設計到材料訂購、從工藝編制到
排版下料、再到設備報驗出廠,每個環節都親身體驗了一次。感覺最有收獲的是編制工藝,繪制排版圖。以前對CAD只是一知半解,會畫簡單的圖形,至于放樣啦、排版啦這些難一點的東西是一竅不通呀,所以一有機會我就跟著我的老師學習。其實排版編工藝是最關鍵的步驟,首先要根據設計圖紙計算出筒體的下料尺寸,一般壓力容器給出的直徑是內徑,下料時要用中徑(也就是內徑加筒體厚度)展開計算,以此算出封頭和底座的下料尺寸;然后要和鋼材經銷商詢問目前所用材質的鋼板的規格尺寸,根據經銷商給提供的規格尺寸進行排版,再根據圖紙接管的方位圖,來確定焊縫的位置,防止將來接管開孔趕到焊縫上(標準規定接管開孔不允許開在焊縫上);排版圖確定了,接著根據工藝員給的板材規格尺寸定料。這次我最大的收獲就是學會了使用CAD如何展開放樣排版,給大家展示一張我做的排版圖這是25m3噴吹罐封頭與下椎體的下料排版圖,這只是其中的一部分,其實做排版圖的目的還是為了節約材料,控制成本。2
焊接工藝指令卡的選擇在壓力容器中也很重要的,以公司現用的焊接工藝評定為依據,根據容器的實際尺寸和公司的焊接設備確定選用何種焊接方法,已達到高效益高質量的完成制作任務為目的。這次的焊接方法是我選的使用埋弧自動焊,容器直徑能滿足這種焊接方法,埋弧自動焊焊接效率高、外觀成形美觀、內在質量容易保證、勞動強度小,操作技術也成熟,再說了我徒弟在當然沒問題嘍,所以我選擇這種焊接方法,焊接參數嚴格按焊接工藝評定執行。實踐證明我的選擇是對的,最終的結果是所有的焊縫98%以上一次探傷通過。
制作過程中我還使用一種新的卷板方法,為公司提高效益,降低成本又邁出了新的一步。以前我們筒體卷制時采用下料長度加長400-500mm,卷制好時再用割槍把兩頭多余的料割掉,這樣既浪費了主材,又不利于下一步的焊接。于是我采用了在外地學來的一種新的卷制方法,我用的是凈料卷板,先將板卷成D字型筒體見下圖:
里面還可以使用埋弧自動焊,這就節省了材料、人工。等埋弧自動焊焊接完成后,再進行找圓。我給筒體找的橢圓度,絕對可以達到標準誤差范圍的要求。比筒體卷板留直邊要強得多。我這個卷圓的小竅門關鍵是要把握卷D字型時接口不能撅嘴,輕微向里凹點可以,卷D字型時不要出死彎,彎曲弧度越大越容易找圓。這樣一節筒體就能節約155㎏的料,這個工程下來就能節約3噸多料。本次工程共買鋼材65噸,照這樣計算材料成本節約了4%之多。
三、實踐收獲與體會
這次畢業實踐,我的目標是抓好管理、控制質量、節約成本,幫助廠長把這次的任
務按期交工。實際工作中我利用在電大學到的知識充實到自己的頭腦中來,兢兢業業的工作,統籌安排時間,每道工序銜接良好,嚴格控制每個質量檢查點,絕不放過任何一個有瑕疵的地方,工作做到精益求精,為公司創造更大的效益。這次所獲得的實踐經驗將對我終身受益,在我畢業后的實際工作中將不斷的得到驗證,我會不斷的理解和體會實習中所學到的知識,在未來的工作中我將把我所學到的理論知識和實踐經驗不斷的應用到實際工作來,充分展示自我的個人價值和人生價值。為實現自我的理想和光明的前程努力。
12秋建筑與施工管理專科
*****
2014-5-24
第二篇:建筑施工管理實習報告
建筑工程學院2014屆頂崗實習報告
目錄
一、(一)
(二)總體概述..............................2 公司簡介...............................2 工程概況...............................2
二、(一)
(二)實習內容..............................2 實習崗位...............................2 崗位職責...............................2
三、實習經驗與分析.........................2
測量定位...........................3
模板工程質量通病防治措施.......................3
鋼筋工程質量通病防治措施.......................3 混凝土工程質量通病防治措施..........................4(一)(二)(三)(四)
四、五、工作總結..............................6 致謝...............................7
一、總體概述
(一)公司簡介
××建工集團總承包公司是××建工集團旗下的一家全資子公司。其前身為××建工集團有限責任公司總承包部,是以建筑、安裝為主業的國有建筑企業,具有房屋建筑工程施工總承包和市政公用工程施工總承包壹級資質,擁有地基與基礎工程、土石方工程、建筑裝修裝飾工程、堤防工程、機電安裝工程、消防設施工程專業承包貳級資質。
(二)工程概況
1.本工程為“鳳江綠緣”住宅樓項目,本項目基地處在××市南郊良鳳江國家森林公園附近,位于××大道延長線以南,××路以東,地上24層,地下2層,屋面高75.30米,建筑類別為丙類,防火為甲級,抗震等級為:剪力墻四級,框架四級;
2.室內±0.000為相當于絕對標高99.100m;
3.結構的設計使用年限為50年;結構的安全等級為二級;
4.抗震設防類別為丙類,抗震設防烈度為6度,地震作用和抗震措施均為6度;
5.地基基礎設計等級及樁基礎設計等級為乙級;建筑物的耐火等級為一級;
6.地下室防水混凝土的設計抗滲等級為P8,地下室防水等級二級;
7.砌體結構施工質量控制等級B級。
二、實習內容
(一)實習崗位
土建施工員
(二)崗位職責
8.負責施工組織和實施,保證工程進度,組織施工測量;
9.負責協調各工種之間的施工矛盾,控制施工材料及保證供應,配合項目部進行成本管理;
10.負責貫徹施工組織設計意圖,按照工程質量和安全生產保證計劃進行施工管理。
三、實習經驗與分析
(一)測量定位
1.建筑物的軸線,高度及外墻垂直度,必須用全站儀或經緯儀嚴格控制,現澆樓板平整度,必須用水準儀做好水平控制點,確保工程的垂直度及樓板平整度。
2.建筑物的沉降觀察及傾斜測檢:按每完成兩層主體結構后及主體完工后每月進行一次測檢,做好有關的質量記錄,如發現問題應立即通知有關部門及負責人處理。
(二)模板工程質量通病防治措施
模板安裝前,先檢查模板的質量,不符質量標準的不得投入使用。
1.梁模板
通病現象:梁身不平直、梁底不平及下撓、梁側模炸模、局部模板嵌入柱梁間、拆除困難。
防治措施:支模時應遵守邊模包底模的原則,梁模與柱模連接處,下料尺寸一般應略為縮短;梁側模必須有壓腳板、斜撐、拉線通直后將梁模釘固。梁底模板按規定起拱;混凝土澆筑前,模板應充分澆水濕潤。
2.柱模板
通病現象:暴模、斷面尺寸鼓出、漏漿、混凝土不密實,或蜂窩麻面、偏位、柱身扭曲。
防治措施:根據規定的柱箍間距要求釘牢固;成排柱模支模時,應先立兩端柱模,校直與復核位置無誤后,頂部拉通長線,再立中間柱模;四周斜撐要牢固。
3.板模板
通病現象:板中部下撓,板底混凝土面不平。
防治措施:樓板模板厚度要一致,櫊柵用料要有足夠的強度和剛度,櫊柵面要平整;支頂要按方案執行;板模按規定起拱。
(三)鋼筋工程質量通病防治措施
1.豎向鋼筋偏位質量通病的防治措施
在立框架柱模板支撐系統前,宜在現澆混凝土樓面上預埋φ12的鋼筋頭或φ48的短鋼管作為支點,間距不大于1m,并使斜支撐能與支點有牢固的連接,起到撐頂、反拉和調節垂直度的作用。
鋼筋放樣時注意梁、柱筋的排列,盡量減少豎向主筋因排列問題而產生的位移。
在梁柱節點鋼筋密集處,在柱與梁頂交界處,扎筋時給框架柱增加一個限位箍筋,用電焊將它與梁的箍筋點焊固定,再將柱主筋逐一綁扎牢固,并沿柱高臨時綁扎間距不大于@500的箍筋,確保節點處柱筋在澆搗混凝土時不會發生偏位。
加強混凝土的現場澆筑管理工作,認真進行技術交底,嚴禁將整車或整料斗的混凝土直接灌注到柱、墻內,不得隨意沖撞構件的鋼筋骨架。均勻下料,分層澆筑,分層振搗,這樣既能保證混凝土的施工質量,又可防止撞偏鋼筋骨架。
在進行豎向鋼筋的搭接、焊接和機械連接前應先搭好腳手架,在上部通過吊線,用鋼管固定住上部的托筋位置,使接長的鋼筋能準確地套在箍筋范圍內,這樣在腳手架上安裝柱的鋼筋,綁扎箍筋,既安全,又能保證框架柱骨架不扭曲、不傾斜,還能提高工效。
2.鋼筋綁扎與安裝
鋼筋骨架外形尺寸不準:綁扎時宜將多根鋼筋端部對齊,防止綁扎時,鋼筋偏離規定位置及骨架扭曲變形。
保護層砂漿墊塊應準確,墊塊步距取800×800,否則導致平板懸臂板面出現裂縫,梁底柱側露筋。
鋼筋骨架綁扎完成后,會出現斜向一方,綁扎時鐵線應綁成八字形。左右口綁扎發現箍筋遺漏、間距不對要及時調整好。
柱子箍筋接頭沒錯開放置,綁扎前要先檢查:綁扎完成后再檢查,若有錯誤應即糾正。澆筑混凝土時,受到側壓鋼筋位置出現位移時,就及時調整。
(四)混凝土工程質量通病防治措施
1.蜂窩
產生原因:振搗不密實或漏振;模板縫隙過大導致水泥漿流失,鋼筋較密或石子相應過大。
預防措施:按規定使用和移動振動器。中途停歇后再澆搗時,新舊接縫范圍要小心振搗。模板安裝前應清理模板表面及模板拼縫處的黏漿,才能使接縫嚴密。若接縫寬度超過2.5mm,應予以填封,梁筋過密時應選擇相應的石子粒徑。
2.露筋
產生原因:主筋保護層墊塊不足,導致鋼筋緊貼模板;振搗不實。
預防措施:鋼筋墊塊厚要符合設計規定的保護層厚度;墊塊放置間距適當,鋼筋直
徑較小時墊塊部距宜密些,使鋼筋自重撓度減少;使用振動器必須待混凝土中氣泡完全排除后才能移動。
3.麻面
產生原因:模板表面不光滑;模板濕潤不夠。
預防措施:模板應平整光滑,安裝前要把粘漿清除干凈,澆搗前對模板要澆水濕潤。
4.孔洞
產生原因:在鋼筋較密的部位,混凝土被卡住或漏振。
預防措施:對鋼筋較密的部位(如梁柱接頭)應分次下料,縮小分層振搗的厚度;按照規程使用振動器。
5.縫隙及夾渣
產生原因:施工縫沒有按規定進行清理和澆漿,特別是柱頭和樓梯施工縫。
預防措施:澆注前對柱頭、施工縫、樓梯施工縫等部位重新檢查,清理雜物、泥沙、木屑。
6.墻柱底部缺陷(爛根)
產生原因:模板下口縫隙不嚴密,導致漏水泥漿;或澆筑前沒有先澆灌足夠50mm厚以上水泥砂漿。
預防措施:模板縫隙寬度超過2.5mm應予以填塞嚴密,特別防止側板吊腳;澆注混凝土前先澆50-100m厚的水泥砂漿。
7.梁柱結點處(接頭)斷面尺寸偏差過大
產生原因:柱頭模板剛度差,或把安裝柱頭模板放在樓層模板安裝的最后階段,缺乏質量控制和監督。
預防措施:安裝梁板模板前,先安裝梁柱接頭模板,并檢查其斷面尺寸、垂直度、剛度符合要求才允許接駁梁模板。
8.樓板表面平整度差
產生原因:振搗后沒有用托板、刮尺抹平;梯級和斜水部位沒有符合尺寸的模具定位;混凝土未達終凝就在上面行人和操作。
預防措施:澆搗樓面應使用托板或刮尺抹平,梯級要使用平直、厚度符合要求的模具定位;混凝土達到1.2Mpa后才允許在混凝土面上操作。
9.混凝土表面不規則裂縫
產生原因:一般是淋水保養不及時,濕潤不足,水分蒸發過快或厚大構件溫差收縮。預防措施:混凝土終凝后立即進行淋水保養;高溫或干燥天氣要加麻袋等覆蓋,保持構件有較久的濕潤時間。大體積混凝土施工方案專項方案執行。
10.缺棱掉角
產生的原因:投料不準確,攪拌不均勻,出現局部強度低;或拆模板過早,拆模板方法不當。
預防產生的措施:指定專人監控投料,投料計量準確;攪拌時間要足夠;拆模應在混凝土強度能保證其表面及棱角在拆除模板不受損壞時方能拆除。拆除時對構件棱角應予以保護。
11.鋼筋保護層墊塊脆裂
產生的原因:墊塊強度過低;沉置鋼筋籠時沖力過大。
預防產生的措施:墊塊的強度保證達要求,并能抵御鋼筋放置時的沖擊力;當承托較大的梁鋼筋時,墊塊中應加鋼筋或鐵絲增強。
四、工作總結
通過半年的頂崗實習,不僅磨練了吃苦耐勞的意志,也看開闊了視野,擴大了知識面。使我了解建筑施工的全過程并初步掌握了建筑施工管理的主要內容、程序和方法,增強了實踐能力同時也加深了對理論知識的理解。
實習期間,我還深深體會到為人處事的原則:待人真誠友好,不要浮華虛偽,跟社會上每個人打交道都要有一顆熱忱的心;虛心學習,積極主動,不要自以為是、自高自大;說話注意分寸與技巧,要大方得體,輕重適宜、恰當合理、兼顧多方;細致深入.無論做什么事情都不要浮于表面,只知其
一、不知其二,明其事更應該明其理.不要半懂不懂,一定要深入的了解。
實習期間,我也發現自己存在的不足,主要有以下幾點:
(一)、專業知識掌握的不夠全面。當前所掌握的知識面不夠廣,對最新的施工規范沒有熟練掌握,致使不能很快地判斷出施工的對錯。因此要在在實踐中不斷地學習,才會掌握更多專業知識和技能。
(二)、專業實踐閱歷遠不夠豐富。由于專業實習時間較少,因此很難將所學知識運用與實踐中去,通過實踐所獲取的閱歷更是很短缺。所以,今后我們在工作崗位上,一
定要抓住機會,多向從事建筑工程的前輩學習,同時要轉換學習方法和態度,改變以往過于依賴老師的被動吸收學習方式,應主動積極向他人學習和請教,同時加強自學能力和駕馭解決難題的本領。
(三)、專業知識在工程中運用不夠靈活。這主要是對所學的知識沒有形成一套完整的體系,這些零散的知識點運用起來很困難,因此,今后在學習和實踐中應該重視積累和運用,使所學的知識由量變到質變,發揮更大的指導作用。
五、致謝
首先感謝廣西建工集團建筑工程總承包有限公司為我提供這次寶貴的實習機會,同時感謝同事們的悉心指導。最后我非常感謝學院的老師,一直以來老師們給了我很多幫助和支持。在此,謹向老師們致以誠摯的謝意和崇高的敬意!
第三篇:建筑施工管理測量實習報告
山東廣播電視大學社會實踐考核表
實 踐 課 題 測量實訓報告
建筑施工管理測量實習報告
中央廣播電視大學專科10春建筑施工管理侯成龍
這次實習的內容是對工程測量知識的實踐化,實習的要求是讓每個同學都對工程測量的實際操作能夠達到基本掌握的程度。這次實習與以前的課堂實習相比,時間更加集中、內容更加廣泛、程序更加系統,完全從控制測量生產實際出發,加深對書本知識的進一步理解、掌握與綜合應用,是培養我們理論聯系實際、獨立工作能力、綜合分析問題和解決問題的能力、組織管理能力等方面素質。也是一次具體的、生動的、全面的技術實踐活動。
在實習的第一天,由老師給我們做了實習的動員。在動員會上,常老師強調了本次實習的重要性,并分析了建筑地理條件較復雜及建筑物密集等因素給本次實習帶來的困難。并鼓勵同學們努力克服困難,努力完成本次實習。還講解了儀器操作、搬遷中的注意事項,并要求在實習期間自行保管實習備品。本次實習中需要用到的儀器主要有水準儀、水準尺、腳架、經緯儀。當天我們就正式開始了室外的測量工作。
(二)實習目的1.通過學習建筑施工測量基本知識,了解建筑施工測量的任務和特點,掌握建筑物放樣以及變形觀測的基本方法。
2.通過測量實訓鞏固和加深所學知識,進一步掌握測量儀器的基本操作技能、控制測量方法、地形圖的應用和施工測量的基本方法。
(四)實習心得
為期兩個星期的工程測量學習已經結束了,通過這次實習,讓我深刻明白了理論聯系實際的重要性。測區是我遼寧工程技術學院校區,雖然測區比較大,基本上是整個學校,測繪圖也是我們整個學校的平面圖,為了能盡快地完成任務,我們小組星期
六、星期天加班進行測量,我們在測量的過程中也并不感到累,也沒有感到辛苦,反而還能自得其樂。
測量學首先是一項精確的工作,通過在學校期間在課堂上對測量學的學習,使我在腦海中形成了一個基本的、理論的測量學輪廓,而實習的目的,就是要將這些理論與實際工程聯系起來。測量學是研究地球的形狀和大小以及地面點位的科學,從本質上講,測量學主要完成的任務就是確定地面目標在三維空間的位置以及隨時間的變化。在信息社會里,測量學的作用日益重要,測量成果做為地球信息系統的基礎,提供了最基本的空間位置信息。構建信息高速公路、基礎地理信息系統及各種專題的和專業的地理信息系統,均迫切要求建立具有統一標準,可共享的測量數據庫和測量成果信息系統。因此測量成為獲取和更新基礎地理信息最可靠,最準確的手段。測量學的分類有很多種,如普通測量學、大地測量學、攝影測量學、工程測量學。作為建筑施工管理系的學生,我們要學習測量的各個
方面。測繪學基礎就是這些專業知識的基礎。
通過這次實習,學到了測量的實際能力,更有面對困難的忍耐力;也學到了小組之間的團結、默契,更鍛煉了自己很多測繪的能力。首先,是熟悉了水準儀、經緯儀的用途,熟練了水準儀、經緯儀的各種使用方法,掌握了儀器的檢驗和校正方法。其次,在對數據的檢查和矯正的過程中,明白了各種測量誤差的來源,其主要有三個方面:儀器誤差(儀器本身所決定,屬客觀誤差來源)、觀測誤差(由于人員的技術水平而造成,屬于主觀誤差來源)、外界影響誤差(受到如溫度、大氣折射等外界因素的影響而這些因素又時時處于變動中而難以控制,屬于可變動誤差來源)。了解了如何避免測量結果錯誤,最大限度的減少測量誤差的方法,即要作到:(1)在儀器選擇上要選擇精度較高的合適儀器。(2)提高自身的測量水平,降低誤差水平。(3)通過各種處理數據的數學方法如:距離測量中的溫度改正、尺長改正,多次測量取平均值等來減少誤差。第三,除了熟悉了儀器的使用和明白了誤差的來源和減少措施,還應掌握一套科學的測量方法,在測量中要遵循一定的測量原則,如:“從整體到局部”、“先控制后碎部”、“由高級到低級”的工作原則,并做到“步步有檢核”。這樣做不但可以防止誤差的積累,及時發現錯誤,更可以提高測量的效率。通過實踐,真正學到了很多實實在在的東西,比如對測量儀器的操作、整平更加熟練,學會了數字化地形圖的繪制和碎部的測量等課堂上無法做到的東西,很大程度上提高了動手和動腦的能力。
我們在這次的實習中,也了解到了要想很好地進行測量,首先必須要掌握過硬的基本理論知識,要有實干精神,每個組員都必須親自實踐,而且要分工明確,工作也可以交換來做,還需要知道失敗乃成功之母,在實習測量的過程中,不可能完全的沒有錯誤,我們應該不氣餒,繼續一次又一次的重測,重計算,一次次地練習,一次次得提高測量水平,我們不斷在經驗中獲得教訓。而且也多虧了老師的指導,我們實習之初,遇到了各種各樣的困難,多虧的老師的耐心講解,才使我們解決了不少測量中的難題。
我們在實習過程中,不可避免的遇到了一些困難,在我們實現之初,我還有點擔心自己不會測,測不好,擔心只有兩個星期的測量時間,自己不能按時的完成任務,但是,經過我們小組的反復測量,我們的團結、默契,克服了測量中的種
種問題,終于按時完成了任務。在測量實習的過程中,我們也遇到了各種各樣的困難。比如:
(1)立標尺時,標尺除立直外,還要選在重要的地方。因此,選點就非常重要,點一定要選在有代表性的地方,同時要注意并非點越多越好,相反選取的無用點過多不但會增加測量,計算和繪圖的勞動量和多費時間,而且會因點多而雜亂產生較大的誤差。
(2)在用水準儀和經緯儀測量的過程當中,有的過程出現了大的誤差,經過我們的重新測量計算,誤差范圍也減小到了可以允許的范圍里。
(3)還有就是計算問題,計算必須由兩個人完成,一個初步的計算,一個檢驗,不過,在此過程當中,也還是出現了計算錯誤的問題,我們在不斷的重復檢驗之中算出了正確的數值,盡量讓誤差減少到了最少。
通過實際的測量實習,讓我學到了很多實實在在的東西,比如對儀器的操作更加熟練,學會了地形圖的繪制和碎部的測量等課堂上無法做到的東西,很大程度上提高了動手和動腦的能力,同時也拓展了與同學的交際、合作的能力。一次測量實習要完整的做完,單單靠一個人的力量和構思是遠遠不夠的,只有小組的合作和團結才能讓實習快速而高效的完成。
第四篇:新疆電大建筑施工與管理專業畢業實習報告(范文)
新疆廣播電視大學
“人才培養模式改革和開放教育試點”
建筑施工與管理專業(專科)
實習報告
學 號: 姓 名: 指導教師: 教 學 班: 分校工作站:
***33 付 華 真 魏
海
林 2012秋建筑施工與管理 省 直 電 大
時間:年 月 日
目錄
一、實習目的 ··································································································· 1
1、實習的意義 ····································································································································· 1
2、實習要求 ········································································································································· 1
二、實習內容 ··································································································· 2
1、工程概況 ········································································································································· 2
2、實習過程 ········································································································································· 2
3、實習收獲 ········································································································································· 4 3.1圖紙會審 ······························································································································· 4 3.2施工準備 ······························································································································· 4 3.3施工協調管理 ······················································································································· 6 3.4抹灰工程: ··························································································································· 7 3.5 混凝土的澆注 ······················································································································ 8
三、實習感悟: ······························································································· 9
四、參考文獻: ····························································································· 11
3)對組織的專業參觀、專業報告都要詳細記錄并加以整理。
二、實習內容
1、工程概況
工程名稱:常州河苑花園小區 建筑面積:21萬㎡
結構層數:地上6層(局部7層)設計單位:常州規劃設計研究院
項目總承包單位:常州華豐建設開發有限公司 施工總承包單位:上海華宏建筑發展有限公司 開工竣工日期:2010年3月9日----2010年11月30日
2、實習過程
我們進入工地的日期是2010年7月13日,此時部分工程結構基本框架部分已經完成,個別結構主體已經完工,要開始安裝裝飾工程的施工了。但仍有部分主體沒有完成,這就給了我們學習到更多東西的機會。
進入工地的前幾天我們重點熟悉施工圖紙和參觀工地。在之前的學習過程中,對施工圖紙以及用處,有的只是理論層面的認識,讀的施工圖也都是比較典型常見的圖,但看到這樣真正用于施工的成體系、成整體的圖紙還是第一次,包括了建筑施工圖、結構施工圖、安裝施工圖、裝飾施工圖以及玻璃幕墻安裝施工圖等幾個部分,每個部分都是一本圖紙。這讓我深刻的體會到土木工程建設是一個龐大的工程,需要各部門的通力合作。而且這些圖紙表面磨損很嚴重,我想大概是經常需要在施工過程中臨時參考圖紙,針對不同的問題由施工方和設計人員結合圖紙提出不同的解決方案。
在閱讀圖紙的過程中,發現了圖紙中的一些問題,為此我請教了一些技術人員,技術人員告訴我,這些問題他們已經發現,并且準備進行會審,為此他給我講解了一些關于圖紙會審的知識,之后我查閱了相關資料,收獲頗豐。
在參觀了工地之后,我不由得對如此復雜的工程產生了強烈的好奇之心,“萬丈高樓平地起”,那么這樣的一棟建筑又是如何開始的呢?遺憾的是我沒有從工程開始的第一天就來到這里,不過幸好我們的技術人員非常熱情的對我講解了工程開始之前的一些準備工作和管理工作的一些協調工作,使我感慨良多。
在實習期間,我與技術人員、工人師傅建立了良好的師生關系。互相經常交流思想,尊重實習指導人的指導和安排。一進入實習工地,首先對整個工程及工
一方面在校期間要學好專業課,使自己具有較高的專業水平。
3、實習收獲
在實習過程中,有一些主體工程沒有完成,我們也有幸有這個機會學習主體構造的建造方法,在這里,我將實習過程中學習到的知識和注意事項做一個總結: 3.1圖紙會審
圖紙會審,施工單位、監理等單位及其他各個專業的工程技術人員針對圖紙肯定或可能存在的影響工程質量的問題,對圖紙的優化建議以文字性匯報材料分發會審人員討論達到合理效果。
圖紙會審可采用全部圖紙集中會審、分部圖紙會審、分階段圖紙會審及分專業圖紙會審等,具體會審形式由監理確定。各個參建單位對施工圖、工程聯系單、及圖紙會審記錄做好備擋工作。作廢的圖紙設計以書面形式通知,各個施工單位自行處理,不得影響施工建設。
圖紙會審應嚴格堅持先大后小、先重點后一般的基本原則進行。即始終圍繞著減少施工難度、提高我方經濟效益、降低生產成本、提高生產效率、有利于工程質量、確保施工安全,加快施工進度的各項目標而展開,最后進行圖紙糾錯并進行圖紙的最后確定及相關的輔助措施的確定。
參加圖紙會審人員一般包括:
建設方:現場負責人員及其他技術人員;
設計方:設計院總工程師、項目負責人及各個專業設計負責人; 監理方:項目總監、副總監及各個專業監理工程師;
施工單位:項目經理、項目副經理、項目總工程師及各專業相關技術負責人; 其他相關單位:技術負責人以及現場負責人。3.2施工準備
施工準備工作一般包括施工物資準備工作和技術準備工作。3.2.1物資準備
工程開工前應落實好材料貨源,并要對準備進場的材料進行嚴格的預測試,測試合格再獲得監理工程師同意,方可采用購到工地,并按照進度計劃,與供貨單位訂好正式供給合同,確保施工中不發生停工等料的誤工情況。準備足夠機械設備,以滿足突擊施工的需要,并準備充分的備用機械。對各種設備及機械進行預檢修,達到性能良好和安全可靠的標準后,方可進場使用。并備足常用配件,確保施工中不發生大的損失和修理,從而不影響施工質量和進度。
邊,縱向到底的逐層管理,做到責任落實到人,從保護自己亦保護他人。財務科負責對施工隊進行工程拔款控制,并進行工程成本考核與分析,隨時提供這方面的報告,供項目經理進行決策。
機材科統一控制全合同段內各種大宗材料的購置和保管,做到有計劃、高質量、低價格、監控好各施工隊自購材料的質量和價格,最大限度地降低工程材料的成本,堵塞漏洞。
綜合辦公室負責項目部內日常生活、生產后勤事務,以及對外協調、處理與當地政府、村鎮百姓的關系,創造一個良好的周邊環境,以利于工程施工。3.3施工協調管理 3.3.1內部施工隊的協調
在施工過程中,項目部對各個施工隊的設備、人員、資金以及施工場地等進行合理安排和調控,以達到最佳的施工效率和效益。3.3.2監理工程師的協調
在施工全過程中,嚴格按照業主和監理工程師批準的施工規范、施工組織設計進行對各作業隊的質量管理,在作業隊自檢、項目部專檢的基礎上,接受監理工程師的驗收和檢查,并按照監理要求,予以整改確保工程的無誤進行。
貫徹業主和監理工程師制定的質量控制、檢查、管理制度,并據此對各施工隊予以控制,確保工程達到檢驗合格,堅決杜絕現場施工隊和包工隊不服從監理工程師的不正常現象發生,使監理工程師的一切指令得到全面執行與貫徹。
所有進入現場使用的成品、半成品材料,設備、器具、均主動向監理工程師提交產品合格證或質保書,應按規定使用前需進行物理化學試驗檢測的材料,主動遞交檢測結果報告,使所使用的材料、設備不給工程造成浪費。
按部位或分項工序檢驗質量的工程,嚴格執行“上道工序不合格,下道工序不施工”的原則,使監理工程師能順利開展工作。對可能出現的工作意見不一的情況遵循“先執行監理的指導,后予以磋商統一”的原則,在現場質量管理中,維護好監理的權威性。
3.3.3與設計單位間的工作協調
如果中標,我單位立即同設計代表取得聯系,進一步了解本工程的設計意圖及工程要求,聽取設計代表對我單位的施工實施方案提出建議。
積極參與設計深化工作,主持施工圖審查,完善設計內容。對實際施工中發現的設計不妥之處,以及不適應實際地形、地質的細部設計,或由于地質、地形
③彈出準線和墻裙、踢腳板線:裝飾工程進行前,一般要用水準儀在墻上放出一根50基準線(距樓面標高50cm),用該線上翻或下翻來控制頂棚、地面標高和墻裙、踢腳板上口水平線。
3.4.2抹灰施工順序和基本要求
①抹灰施工順序:一般先外墻后內墻、先頂棚、墻面后地面。外墻由屋檐開始自上而下,先抹陽角線、臺口線,后抹窗和墻面,再抹勒腳、散水和明溝;內墻和頂棚應在屋面防水完工后進行,一般先房間后走廊,再樓梯和門廳。
②分層抹灰:底層抹灰厚度一般5~9mm,作用是使抹灰層與基層牢固結合,并對基層初步找平,底層涂抹后應間隔一定時間,讓其干燥和水分蒸發后再涂抹中間層和罩面層;中間層起找平作用,可一次或分次涂抹,厚度約5~12mm,在灰漿凝固前應交叉刻痕,以增強與面層的粘結;面層厚度一般為2~5mm,應確保表面平整、光滑、無裂紋。
③抹灰層厚度:抹灰層厚度一般為15~20mm,最厚不超過25mm。室內墻裙和踢腳板一般要比罩面層凸出3~5mm。在加氣砼基層上抹灰時,其底灰和中間層的灰漿強度宜與加氣砼強度相近,底灰宜用中砂,中層和罩面層宜用中砂。水泥砂漿不得抹在石灰砂漿層上。
④細部構造:外墻窗臺、窗楣、雨篷、陽臺、壓頂和突出墻面腰線等,上面應做流水坡度(一般10%),下面應做滴水線或滴水槽,其深度和寬度均不小于10mm。
3.5 混凝土的澆注 3.5.1原材料試驗
混凝土面層水泥采用硅酸鹽水泥。水泥進場時應有產品合格證及化驗單,并對水泥的品種、標號、包裝、數量、出廠日期進行檢查驗收。不同標號、廠牌、品種、出廠日期的水泥,不得混合堆放,嚴禁混合使用。出廠期超過2個月或受潮的水泥,堅決棄之不用。已經結塊變質的水泥不得使用。砂采用潔凈、堅硬,符合規定級配,細度模數在2.5以上的粗、中砂。砂的技術要求要符合規范的規定。石子要求質地堅硬、耐久、潔凈、有良好的級配。顆粒應接近立方體,最大粒徑不超過40mm。混凝土摻用的外加劑,經配合比試驗符合要求方可使用。外加劑應符合《混凝土外加劑》(GB/T2847)的規定。3.5.2 配合比設計和控制
采用干硬性混凝土,配合比設計時坍落度為0~2cm。混凝土配合比要保證混
由于施工方的水平有限,也難免會出現各種大小問題,師傅就會找項目經理或施工員談話,要求認真對待,我也從中學到了一些質量控制的知識。
這次施工實習雖然時間很短,但是我不但學到了很多施工技術,管理方面的基本知識,還學到了監理專業的一些常識,并且經常深入工地,在第一線進行學習,理論與實踐相結合,在短短幾天內,個人能力得到了一定的提升,并且在工作中得到了師傅們和總監的認可,總監也對我的工作給與了比較高的評價。我在工作中,學會了融入團隊中來,依靠團隊的力量,解決困難的問題。熱情對待工作,對待周圍的人。
在實習的過程中,我越來越覺得人際交往的重要性。而人際交往最重要的是首先要尊重人,無論是一線工人還是項目經理,都要謙遜對待,其次是自己要主動交流自己的想法,這樣能第一時間糾正自己錯誤的理解,第一時間接觸最新的情況,更扎實的打好專業基礎。
0
第五篇:建筑施工實習報告
建筑施工實習報告
經過學校的安排我于2012年12月10日~2012年12月14日進行了一個星期的建筑施工實習,這次實習是書本和實踐相互結合很好機會,經過這次實習讓我受益匪淺。
一 工程簡介
(1)建業桂園:本工程為平頂山建業桂園二期工程,位于平頂山新城區龍翔大道與育英路交叉口西北角。本期工程建筑面積189284.03m2,其中地下建筑面積33230.44m2,地上建筑面積156053.59m2。住宅地上33層(共6棟),30層(1棟),公寓為6層,沿街商業及幼兒園2層;結構安全等級為二級,結構抗震等級住宅樓地下室1層及以上三級,地下室2層四級,幼兒園,公寓兩層商業為四級。
(2)德馨苑公共租賃住宅小區:該小區的建筑面積為37222.74平方米,在2012年11月2日開工,計劃竣工日期為2014年3月11日。該建筑抗震等級為4級,抗震設防烈度為6度,使用年限為50年。
(3)榮邦大廈:該大廈規劃面積5138.4平方米,設計為地上17層地下1層的辦公樓,總面積22017.65平方米。這棟建筑是框剪結構。二 實習內容
1)鋼筋的種類及外形特征; 2)鋼筋的焊接辦法及品質規定; 3)鋼筋的綁扎的辦法及品質規定; 4)鋼筋綁扎的搭接長度規定;
5)了解土方工程的特點及回填土的質量的要求,了解屋面防水及地下防水的施工方法; 6)了解混凝土澆筑前應對對模板及其支架以及鋼筋工程的檢查工程;
7)了解磚墻的砌筑方法,了解墻體的構造要求;了解墻面,地面的施工要求; 8)通過查閱資料懂得施工組織和概預算的編制方法。
三 心得體會
一、基坑支護:包括基坑支護方案、土方開挖方案、支護變形監測、沉降觀測、基坑支護驗收。
基坑開挖之前,要按照土質情況、基坑深度以及周邊環境確定支護方案,其內容應包括:放坡要求、支護結構設計,機構選擇,開挖時間、開挖順序、分層開挖深度、坡道位置、車輛進出道路、降水措施及監測要求等,針對施工工藝結合作業條件,對施工過程中可能造成坍塌的因素和作業人員的安全以及防止周邊建筑、道路等產生不均勻沉降,制定具體可行的施工方案。
深基坑施工時,土側壓力加大加上地下水的出現,必須做專項支護設計以確保施工安全。基坑(槽)開挖時,會發生一些不可預見的因素,都會引起坍塌事故的發生,所以,應有土方開挖方案,必須有人負責支護變形監測,特別是雨后和解凍期,如果發現邊坡或坡頂處有裂縫,疏松,或支撐有折斷,走動等危險跡象時,應立即采取加固措施。
深基坑施工時,邊坡或支撐的松動,降排地下水,局部流砂現象等,都可能引起附近土層的變動,因此應對毗鄰建筑物和重要管線和道路進行沉降或位移觀測,以便及時采取措施,阻止沉降或位移的發展。
基坑支護驗收是在基坑支護完成后,對基坑支護情況進行驗收。
二、模板工程:包括模板施工方案、模板工程驗收、拆模申請、支、拆模安全交底。施工前,應對邊坡側立面擋土墻模板進行施工設計。模板及其支架的強度、剛度和穩定性應滿足各施工階段荷載的要求,能承受澆筑混凝土的沖擊力、混凝上的側壓力和施工中產生的各項荷載。
模板施工發生問題的主要原因有:模板拆除后,混凝土未達到設計強度,在樓板上堆物過 1 多,使樓板超過允許荷載;現澆混凝土模板支撐,沒有經過設計計算,支撐系統強度不足,在澆注混凝土過程中,造成整體失穩坍塌等。模板安裝完畢,必須由該現場技術負責人組織,按照設計要求檢查驗收后,才能澆筑混凝土。模板支撐的拆除,必須確診混凝土強度達到設計要求時經申報批準后才能進行。支、拆模前,由負責該項施工的工長對作業班組進行書面安全技術交底規定搭拆的操作順序,模板結構和安全操作規程。
三、防水:是非常重要的工程,影響建筑物的壽命和功能發揮。常做部位:地下,屋面,墻面,樓地面。地下防水的施工為了消除所有孔洞造成的滲漏,使接縫嚴實,形成封閉的整體。防水層的施工工藝順序:基面處理→涂布基層處理劑→細部增強→鋪第一(二)層卷材→接縫處理→保護層。該建筑的防水卷材采用的是外貼法:墻體結構→防水→保護(先底后立面)。這種方法結構及防水層質量易檢查,但槽寬大,工期長。搭接長度≮100;上下層錯縫1/3~1/2幅寬。不同的材料不同的防水等級,層數、厚度不同。
四、鋼筋:鋼筋是指鋼筋混凝土用和預應力鋼筋混凝土用鋼材,其橫截面為圓形,有時為帶有圓角的方形。包括光圓鋼筋、帶肋:熱軋鋼筋、余熱處理鋼筋、冷拉鋼筋、冷拔鋼筋、冷軋鋼筋等。HPB235熱軋光圓一級鋼筋、HRB335熱軋帶肋二級鋼筋、HRB400熱軋帶肋三級鋼筋、RRB400余熱處理三級鋼筋。
1)鋼筋的混凝土保護層是指主筋外皮主筋外皮主筋外皮主筋外皮與混凝土面之間的距離。2)鋼筋的錨固長度是指鋼筋伸入支座內的長度。
3)1.直鋼筋的下料長度=構件長度-混凝土保護層厚度+彎鉤增加長度 2.彎起鋼筋下料長度=直段長度+斜段長度-彎鉤調整值+彎鉤增加長度
3.箍筋下料長度=外皮周長-彎曲調整值+彎鉤增加長度(箍筋下料長度=外皮周長+箍筋調整)
4)鋼筋的搭接:綁扎搭接,焊接(閃光對焊,電渣壓力焊)和機械連接。其中綁扎搭接是指兩根鋼筋相互有一定的重疊長度,用鐵絲綁扎的連接方法,適用于較小直徑的鋼筋連接。一般用于混凝土內的加強筋網,經緯均勻排列,不用焊接,只須鐵絲固定。閃光對焊:原理是利用對焊機使兩端金屬接觸,通過低電壓的強電流,待金屬被加熱到一定溫度變軟后,進行軸向加壓頂鍛,形成對焊接頭。鋼筋閃光對焊是將兩根鋼筋安裝放成對接形式,利用焊接電流通過兩根鋼筋接觸點產生的電阻熱,使接觸點金屬熔化,產生強烈飛濺,形成閃光,迅速施加頂鍛力完成的一種壓焊方法。機械連接:通過鋼筋與連接件的機械咬合作用或鋼筋端面的承壓作用將一根鋼筋的力傳遞至另一根鋼筋的連接方法。鋼筋套筒擠壓連接、鋼筋錐螺紋套筒連接、鋼筋徽粗直螺紋套筒連接和鋼筋滾壓直螺紋套筒連接。結構構件中縱向受力鋼筋的接頭宜相互錯開,鋼筋機械連接的連接區段長度應按35 d 計算(d 為被連接鋼筋中的較大直徑)。
五、自動消防系統:一般由火災探測器、區域報警器和集中報警器組成;也可以根據工程的要求同各種滅火設施和通訊裝置聯動,以形成中心控制系統,即由自動報警、自動滅火、安全疏散等組成一個完整的消防控制系統。火災探測器是探測火災的儀器,由于在火災發生的階段,將伴隨產生煙霧、高溫和火光。這些煙、熱和光可以通過探測器轉變為電信號報警或使自動滅火系統啟動,及時撲滅火災。自動控制消防噴淋系統是一種在發生火災時,能自動打開噴頭噴水滅火并同時發出火災報警信號的消防滅火設施。自動噴淋滅火系統具有自動噴水、自動報警和初期火災降溫等優點,并且可以和其他消防設施同步聯動工作,因此能有效控制、撲滅初期火災。現已廣泛應用于建筑消防中。自動消防噴淋系統分為感煙式和感溫式兩種。
六、通風系統:自然通風和機械通風。一般商場辦公區建筑采用機械通風。機械通風機作用使空氣流動,造成房間通風換氣的方法。該通風系統是由室外新鮮空氣在送風機的作用下經過空氣處理設備、送風管道和送風口送入室內,污染后的室內空氣在排風機的作用 2 下直接送出室外或送入空氣凈化處理設備。該系統是由空氣過濾器、空氣加熱器、風機、電動機、風管、送風口、軸流風機構成。
七、價格分析 主要對建材市場的建筑材料墻紙,整體櫥柜,燈具進行價格分析。
墻紙分類:pvc,織物壁紙,紙基壁紙,木纖維壁紙。Pvc墻紙價格比較低廉,但是不環保,不健康。織物壁紙:這種壁紙無毒無塑料味、耐磨,不產生靜電,也不褪色,吸音效果好。室內采用這種壁紙顯得高雅、柔和、舒適,但價格相對較貴。相對來說這種壁紙不便清潔。裝飾效果好,由于壁紙擁有數百種顏色、花紋和圖案,只要按照設計者的意圖施工,就可以達到各種各樣的裝飾效果。紙基壁紙:具有較好的裝飾效果外,還具有吸音、隔熱、防霉、防菌、耐水等多功能。紙基涂塑壁紙具有較好的耐摩擦性和防污染性,便于保持墻面干凈,施工方便。木纖維壁紙:此種壁紙由木漿聚酯合成,采用亞光型光澤,柔和自然,易與家具搭配,花色品種繁多;對人體沒有任何化學侵害,透氣性能良好,墻面的濕氣、潮氣都可透過壁紙;長期使用,不會有憋氣的感覺,也就是我們常說的“會呼吸的壁紙”,是健康家居的首選。它經久耐用,可用水擦洗,更可以用刷子清洗。經過比較覺得木纖維壁紙較適合家庭裝修。
櫥柜:整體櫥柜的價格和要選擇的面板,柜體版,面板材質有很大關系。面板種類有人造板,石英石,大理石,不銹鋼等材質。石英石面板其色調美觀、華貴、硬度高、集天然和人造石之優點于一身,具有刮不花、燙不壞、污不染、用不舊、無毒、無輻射等特點,比其它裝修面材應用在廚房更好。經過比較得出石英石的面板較適合家庭裝修使用。
燈具:價格幅度很大,可根據裝修喜好選擇,但是應選LED燈,節能環保。
經過一周短暫的實習,雖然時間很短,但是獲得了很多知識。我近距離的觀察了整個房屋的建造過程,學到了不少很適用的具體的施工知識,這些知識往往是我在學校很少接觸,很少注意的,但又是十分重要基礎的知識。實踐是課本上知識的運用,我們要學以致用,理論聯合實際。